|
Andrew Avalon, P.E., P.S.P. |
BACKGROUND
SUMMARY
Mr. Avalon is President of Long International and has over 23 years of engineering, construction management and claims consulting experience. He is an expert in the preparation and evaluation of construction claims, business interruption claims, schedule delay analysis, arbitration/litigation support and dispute resolution. He has prepared more than thirty CPM schedule analyses, written expert witness reports, and supported attorneys in depositions, cross-examinations, mediations and settlement negotiations. In addition, Mr. Avalon has published numerous articles on the subjects of CPM schedule analysis and entitlement issues affecting construction claims. Mr. Avalon is a registered Professional Engineer with U.S. and international experience in petrochemical, oil refining, commercial, educational, medical, correctional facility, transportation, dam, wharf, wastewater treatment, and nuclear power projects.
Click
to print resume as a PDF file.
Note: Click on the logo at the top of any page in the PDF file to return here.
EDUCATION
B.S.,
Mechanical Engineering, Stanford University, 1984
B.A., English, Stanford University, 1984
PROFESSIONAL
REGISTRATIONS
Registered
Professional Engineer, Florida (No. 55137)
Registered Professional Engineer, Colorado (No. 25802)
Planning & Scheduling Professional (PSP-00193)
PROFESSIONAL
AFFILIATIONS
Florida
Engineering Society
National Society of Professional Engineers
Project Management Institute, College of Scheduling
Association for the Advancement of Cost Engineering International
TECHNICAL
EXPERIENCE
Representative
U.S. and international technical experience includes:
Construction claims preparation, analysis, defense, and negotiation of settlements on industrial, commercial, institutional, civil, and public works projects.
Identification and systematic evaluation of major engineering and construction problems and their cause/effect relationship on cost and schedule overruns.
Management performance assessments.
Speaker and author of articles and training manuals on the subject of construction claims, CPM schedule analysis, and project management.
CPM schedule analyses of the impacts of delays, disruption, acceleration and loss of labor productivity.
CPM schedule development and monthly progress reporting.
Contract/entitlement analysis.
Direct and indirect damages assessments.
Contract administration and change order preparation and management.
Development of computerized database management
systems.
PROJECT
EXPERIENCE
Mr. Avalon has served as a Project Manager on more than thirty claims ranging in size from $100,000 to over $1 billion. He has evaluated claims and assessed the performance of owners, engineers, and contractors on numerous types of projects, both in the U.S. and internationally. Representative projects include the following:
Petrochemical
and Nuclear Facilities
Analysis of a $150 million claim for schedule delays and disruptions during the construction of two Polyethylene Terephthalate (PET) plants in Argentina and The Netherlands. Prepared and answered interrogatory questions, prepared and answered document production requests, developed an Internet-based document repository database containing over 500,000 pages of project documentation. Attended fact witness depositions to support counsel. Prepared detailed expert reports in support of the ICC arbitration in New York City.
Analysis of a $100 million claim for property damage and $1 billion in business interruption losses resulting from fire damage to a tar sands oil upgrading facility in Canada. Prepared detailed CPM schedule analyses, wrote expert witness reports, assisted attorneys in cross-examination, and assisted expert witnesses prepare for testimony in support of the trial in Canada.
Analysis of a $500 million claim for business interruption losses resulting from fire damage to a tar sands mine facility in Canada. Prepared detailed CPM schedule analyses and an expert witness report. Designated as a CPM expert witness in support of the ICC Arbitration in Canada.
Analysis of a $200 million insurance claim for non-traditional coverages resulting from delays to the construction of a tar sands mine facility and upgrader unit in Canada. Testified as a CPM expert witness in support of the ICC Arbitration in Canada.
Analysis of a $250 million claim for property damages resulting from fire damage to a fractionator tower at an upgrading facility in Canada. Evaluated expediting costs in support of the insurance adjustment process.
Analysis of shutdowns of an MTBE plant in Canada and related loss of production claims. Prepared analyses regarding the causes of the shutdowns and an expert witness report.
Analysis of EPC schedules for a $1.7 billion Gas to Liquids facility in Nigeria. Verified the schedule work scope against contract requirements. Evaluated schedule metrics, reviewed schedule logic, assessed the reasonableness of the critical path and provided recommendations for optimizing the schedule.
Analysis of a $50 million claim for schedule delays and disruptions during the construction of a new oil processing unit in Trinidad and Tobago. Prepared detailed CPM schedule analyses and expert reports in preparation for Uncitral arbitration in London.
Claims preparation, database development and negotiation support related to the design and construction of a $450 million fertilizer plant in Iraq. During this project, Mr. Avalon prepared detailed as-planned and as-built schedule comparisons that were used to successfully negotiate claims between the Japanese prime contractor, one Turkish and two Korean subcontractors.
Preparation of a detailed CPM schedule analysis for a mechanical subcontractor on a Delayed Coker Unit in Puerto La Cruz, Venezuela. Prepared document production requests, developed an Internet-based document repository database containing over 100,000 pages of project documentation. Prepared detailed briefs and was designated as a CPM expert witness in support of the ICC arbitration in Switzerland.
Management audit of a contractor’s $90 million claim on an NC2 Ethylene Cracking Unit in Belgium. Performed a “cold eyes review” of the contractor’s schedule delay analysis.
Claims analysis in support of the owner’s defense against a contractor’s delay and acceleration claim on a $160 million chemical plant facility in Terneuzen, The Netherlands.
Preparation of CPM fragnets depicting schedule delays and analysis of productivity losses on a natural gas liquefaction project in Maracaibo, Venezuela.
Database development including coding over 100,000 documents to facilitate research and analysis for a prudency audit to evaluate the reasonableness of $1.3 billion of start-up and commissioning cost overruns on a large nuclear power plant.
Industrial, Commercial, Educational, Medical and Correctional Facilities
Evaluation of delays and cost overruns on an insulation manufacturing facility in Canada. Analysis of schedule and cost data in support of the Owner’s $28 million counterclaim against the EPC contractor’s $20 million claim. Designated as a CPM expert witness for the arbitration.
Preparation of a damage and schedule analysis on behalf of a general contractor for a $560,000 claim on a new cafeteria building and dormitory renovation project at a youth detention facility in Okeechobee, Florida. Designated as a CPM expert witness for the jury trial and presented preliminary findings at the court ordered mediation which resulted in a successful settlement.
Preparation of a baseline schedule for a classroom addition to an elementary school in Groveland, Florida.
Analysis and review of delay claims submitted by the contractor due to soil contamination caused by underground gasoline tanks on a federal courthouse project in Minnesota.
Preparation and analysis of detailed as-planned and as-built schedules to assist the owner defend against contractor claims on a university dormitory project in Riverside, California.
Preparation of detailed as-planned and as-built schedule analyses on a $45 million dispute involving two hospitals in Kuwait built by an Italian contractor.
Analysis of detailed as-planned and as-built schedules for two state prison projects and on a city prison project in California.
Preparation and analysis of detailed as-planned and as-built schedules for the mechanical contractor on a state prison project in Montana. Prepared schedule delay claims and participated in expert witness depositions.
Evaluation of entitlement and preparation of damage analyses for the contractor for a main post office in Wyoming. Prepared financial analyses and wrote expert reports.
Management advisory services for a concrete drilling and sawing contractor in Minnesota. Assisted contractor in transitioning to new cost accounting software.
Transportation Projects
Preparation of monthly progress reports and schedule updates for the preliminary engineering and final civil design of the $600 million Central Florida Light Rail Transit System in Orlando, Florida. Developed detailed civil design, construction and systemwide interface schedules.
Quality control and reasonableness review of a schedule delay analysis for a tunnel-boring contract on the Los Angeles metro subway project.
Pricing and negotiation of change orders for the Bay Area Rapid Transit District on a $65 million train control contract. Evaluated entitlement, prepared schedule analyses, wrote findings of fact, and negotiated change orders.
Preparation of detailed as-planned and as-built schedule analyses for the contractor on a $100 million airport expansion project in California.
Financial and schedule audits for the Los Angeles County Transportation Commission on light rail and metro subway projects. Reviewed project budgets, contractor schedules, construction manager monthly progress reports, and advised the County of potential cost overruns, schedule delays and reporting deficiencies.
Preparation of detailed as-planned and as-built schedule analyses for the contractor on a highway construction project in Pennsylvania. Assisted the contractor to prepare a recovery schedule to mitigate construction delays caused by differing site conditions.
Dams,
Wharfs and Wastewater Treatment Projects
Preparation of a schedule delay analysis for an underground piping subcontactor in Florida. Designated as a CPM scheduling expert. Claim settled in negotiations after preparation of an expert report.
Preparation of a schedule delay analysis for an underground piping subcontractor in Florida. Designated as a CPM scheduling expert. Claim settled in negotiations after preparation of an expert report.
Preparation of a preliminary damage analysis for an electrical subcontractor on the South Cross Bayou Water Reclamation Project in Pinellas County, Florida. Designated as an expert witness on the electrical subcontractor’s loss of productivity and extended overhead damages. Claim settled in negotiations after preparation of an expert report.
Analysis of a $1.7 million claim for schedule delays and disruptions during the construction of two wastewater treatment plants and barometric condenser conversions at an oil-processing unit in Trinidad and Tobago. Prepared detailed CPM schedule analyses and expert reports in preparation for arbitration.
Preparation of detailed as-planned and as-built schedule analyses for the contractor on an earth-filled dam project in New Mexico. Participated in negotiations between the contractor and the U.S. Bureau of Reclamation that resulted in a $55 million settlement for the contractor.
Preparation of detailed as-planned and as-built schedule analyses for the contractor on a dam in Alberta, Canada. Participated in negotiations between the contractor and the Province of Alberta.
Preparation of entitlement and damage analyses for a hydroelectric pumped storage facility in South Carolina. Performed financial analyses and wrote expert reports.
Evaluation of entitlements and preparation of claim analyses for the contractor for a U.S. Coast Guard wharf at the Port of Los Angeles. Analyzed entitlement issues and wrote expert reports.
Analysis of a contractor’s claim against the owner of a wastewater treatment project in Ohio.
PROFESSIONAL EXPERIENCE
Long International,
Inc.
Orlando, Florida
(July 1999 to Present)
As President of Long International, Mr. Avalon provides CPM scheduling, claims management and dispute resolution services to the construction industry. He specializes in preparing detailed schedule analyses and apportioning responsibility for delays, disruption and acceleration impacts. He is skilled at contract analysis, claims preparation, claims defense and the negotiation of settlements. He has analyzed construction schedules for owners and contractors to determine the causes of construction delays and to equitably allocate responsibility for delay-related costs. He has developed “cause and effect” analyses and presentations for time extensions and delay damages.
Pacific Project
Management, Inc.
Orlando, Florida
(April 1998 to July 1999)
As a Project Manager, Mr. Avalon served as the Senior Scheduler for the preliminary engineering and final civil design of the Central Florida Light Rail Transit System. He developed detailed civil design schedules, construction schedules and systemwide interface schedules, supervised cost engineering functions, participated in weekly project management meetings and schedule interface meetings, and prepared monthly cost and schedule progress reports.
West Engineers and
Associates, Inc.
San Francisco,
California (May 1996 to April 1998)
As a Project Manager, Mr. Avalon served as a Contract Administrator for the Bay Area Rapid Transit District on a $65 million Train Control contract for three BART extensions. He evaluated entitlement of contractor claims, prepared schedule analyses, wrote findings of fact and negotiated change orders. Mr. Avalon received a Letter of Commendation from BART’s Transit System Development Executive Manager for his significant contribution to bringing to fruition five new Stations and 26 miles of track.
Andrew Avalon, P.E.
San
Rafael, California (September 1991 to May 1996)
As an independent consultant, Mr. Avalon prepared detailed CPM schedule analyses, wrote expert witness reports, supported attorneys in cross-examination, and participated in settlement negotiations on large construction disputes. The largest of these projects involved the analysis of a $100 million claim for property damage and $1 billion in business interruption losses resulting from fire damage to a synthetic crude oil refinery in Canada.
Kellogg Corporation
Littleton,
Colorado (November 1986 to September 1991)
As a Senior Consultant, Mr. Avalon prepared and evaluated claims for contractors and owners on major construction projects. He analyzed construction schedules for owners and contractors to determine the causes of construction delays and to equitably allocate responsibility for delay-related costs. He developed “cause and effect” analyses and presentations for time extensions and delay damages. He evaluated the adequacy of construction budgets on major public works projects to allow sufficient contingency for changed conditions, delays and other unforeseen events and reviewed public works expenditures for compliance with federal financing requirements. He also developed document databases, some including over 100,000 documents, to facilitate the research and analysis of construction claims and to prepare for litigation, arbitration or mediation.
General Electric
Company
Denver,
Colorado. (May 1984 to April 1986)
As a Sales Engineer, Mr. Avalon sold electrical distribution equipment including switchgear, transformers and motor control centers for residential and commercial construction projects. He graduated from GE’s Technical Marketing Program in 1985 and achieved 149% of a $1.8 million annual budget in the first quarter of 1986.
PUBLICATIONS AND SPEAKING ENGAGEMENTS
“Retrospective As-Built Schedule Development,” with Dr. Anamaria Popescu, AACE International Annual Meeting, New Orleans, June 2005.
“Schedule and Delay
Analysis Methodologies,” with Dr. Anamaria Popescu, Lorman Education Services
Seminar on “Construction Claims Detection, Prevention and Schedule Analysis in
Texas,” Houston, TX, February 2005
“Cardinal Changes,” with
Richard J. Long, ABC Today,
May 2001.
“Constructive Changes,”
with Richard J. Long, ABC Today,
April 2001.
“Ownership of Float,” with
Richard J. Long, Central Florida AGC
News, April 2001.
“Differing Site
Conditions,” with Richard J. Long, Building
Central Florida, March 2001.
“The ‘No Damage for Delay’
Clause,” with Richard J. Long, Central
Florida AGC News, March 2001.
“Specific Damages Analysis
Method,” with Richard J. Long, Central
Florida AGC News, February 2001.
“Delay Claims,” with
Richard J. Long, Building Central Florida,
January 2001.
“Modified Total Cost
Claims,” with Richard J. Long, Central
Florida AGC News, January 2001.
“Defective and Deficient
Contract Documents,” with Richard J. Long, Building
Central Florida, December 2000.
“Estimating Construction
Claim Damages Using A/B Estimate and Delta Estimate Methods,” with
Richard J. Long, Central Florida AGC
News, December 2000.
“Quantum Meruit,” with
Richard J. Long, Central Florida AGC News,
November 2000.
“The Jury Verdict Method
of Calculating Damages,” with Richard J. Long, Central Florida AGC News, October 2000.
“Total Cost Claims,” with
Richard J. Long, Central Florida AGC News,
September 2000.
“Acts of God / Weather,”
with Richard J. Long, Building Central
Florida, August 2000.
“Quantification of
Damages,” with Richard J. Long, Central
Florida AGC News, August 2000.
“Directed and Constructive
Acceleration,” with Richard J. Long, Building
Central Florida, July 2000.
“Apportioning Concurrent
Delays,” with Richard J. Long, Central
Florida AGC News, July 2000.
“Construction Claim
Types,” with Richard J. Long, Building
Central Florida, June 2000.
“Claims Mitigation During
Construction,” with Richard J. Long, Central
Florida AGC News, June 2000.
“Review and Approval of
Detailed As-Planned Schedules,” with Richard J. Long, Central Florida AGC News, May 2000.
“Schedule Analysis: A
Dispute Resolution Tool,” Bay
Area Primavera User Group, San Francisco, CA, August 1997.
“Claims Analysis Using P3
and Expedition,” with John Stack of Primavera Systems, Inc., Project Management
Institute, Reno, NV, February 1995.
“Evaluating Claims Using
P3 and Expedition,” with Ted Stolarczyk and Jim Coyle of Primavera Systems, Inc.,
Primavera Systems User Conference, Philadelphia, PA, September 1994.
“What Works in American
Industry and What Doesn’t,” Facilitator for satellite broadcast by Peter
Drucker, San Francisco, CA, November 1992.
“Claims Forum, Mock
Arbitration,” Primavera Systems User Conference, Philadelphia, PA, August 1991.
“Evaluating Responsibility
for Schedule Delays,” Nordnet International Project Management Conference,
Trondheim, Norway, June 1991.
“Profitable Claims
Management,” California CPA Society, Construction Industry Conference, Anaheim
and San Francisco, CA, May 1991.
“Resolving and Preventing
Construction Claims,” A one-day seminar sponsored by Kellogg Corporation,
Dallas, TX, March 1991.
“Schedule Analysis: A
Dispute Resolution Tool,” KC-News,
December 1990.
“Quantifying and
Evaluating Schedule Delays,” Primavera Systems User Conference, Philadelphia,
PA, September 1990.
“When is the Total Cost
Approach Valid for Damages?” CFMA Building
Profits, March/April 1990.
“Constructive Change - An
Unwritten Bill of Rights for Contractors,” Construction
Digest, March 1990.
“When Fairness is not
Enough,” Editorial, KC-News,
September 1989.
“Maladministration, As It
Affects the Professional Roof Consultant,” Roof Consultants Institute National
Convention, Washington, D.C., March 1989.
“Maladministration - When
the Owner’s Actions or Inactions Interfere,” Walker’s Estimating and Construction Journal,
Spring 1989.
“Contract Clauses and The
Project Schedule,” with Herbert D. Casner, KC-News,
October 1988.
“Document Discovery in
Construction Litigation,” KC-News,
December 1987.
“Perspectives on Construction-Related Cases,” KC-News, October 1987.
Click to Return to Top of Page
Return to Resumes
| website: www.long-intl.com | email: rlong@long-intl.com | telephone: 303-972-2443 | facsimile: 303-972-6980 |
![]()
Revised: January 08, 2008