Name/Type of Project

Description of Services Provided

Project Location
Computer Microchip Manufacturing Facility Analysis of a mechanical contractor’s contract and quantum meruit claim for disputed changes in scope, delays, and loss of productivity on the installation of piping systems on a computer microchip manufacturing facility. Virginia
Commercial
Buildings
Litigation support for the construction cost overruns and delays for several commercial building projects including a luxury hotel and a major office building. Texas
Educational
Facility
Analysis of a mechanical contractor's $1.5 million claim on a new university classroom building project. Colorado
Educational
Facility
Analysis and presentation of schedule impacts and litigation support services for a public schools district in defense of the general contractor's claims on four elementary schools. Florida
Educational
Facility
Claim preparation including an entitlement analysis, schedule analyses and damage assessment to assist an electrical contractor obtain a time extension and compensation for delays experienced during the construction of a school project. New York
Educational
Facility
Preparation of a $1.2 million delay and disruption claim involving the electrical subcontract work on a new university classroom building project. Washington
Hospital Preparation of a $4 million delay and disruption claim involving the electrical subcontract work on the Native Alaska Medical Center project in Anchorage. Alaska
Hospital Mediation services associated with $6 million in outstanding change orders on a $100 million university hospital modernization project. Performed document discovery and reviewed 200,000 project documents database and damage allocation model. California
Hospital Litigation support services on a $75 million hospital complex. Performed detailed quantity take-offs and developed a 1,100 activity as-built CPM schedule and analyzed actual manpower distribution to evaluate lost productivity issues. California
Hospital Evaluation of the adequacy of the general contractor's project schedule regarding logic relationships, critical path, and use of contraints on a new hospital project. Colorado
Hospital Preparation of detailed as-planned and as-built schedule analyses on a $45 million dispute involving two hospitals built by an Italian contractor. Kuwait
Hospital Schedule and damages analysis for a major mechanical and electrical subcontractor related to delays and disruptions encountered during the construction of a V.A. Hospital project. Michigan
Airport Claim preparation, schedule and damage analyses, and litigation support services for the $100 million John Wayne Airport expansion project. Creation of an as-built CPM schedule to analyze project delays and acceleration issues. Reviewed project documentation and change orders to determine the validity of delays and cause-effect relationships of schedule impacts and damages and created arbitration graphics. California
Airport Bid estimate review and an evaluation and critique of civil work including mass cut, haul and fill operations at the Denver International Airport. Colorado
Airport Project consultant services including change order resolution for the Fire Alarm and Voice Paging Systems for Concourse A, B, and C, the Airport Office Building, and the Terminal Complex at the Denver International Airport. Colorado
Airport Preparation of a detailed CPM schedule to enable a Korean contractor for the Guam International Airport to receive 3 time extensions and a $4.5 million equitable adjustment for delays and impacts. Assisted the project management team to control progress. Guam
Airport On behalf of the owner, performed an evaluation of the contractor's claim on a new airport terminal building project. Wyoming
Convention
Center
Scheduling services for the electrical subcontractor on a major convention center expansion project. Developed and monitored a resource-loaded completion schedule that scheduled and tracked the remaining electrical activities. Illinois
Stadium and Convention Center Management of the preparation of a $6 million delay and disruption claim involving electrical subcontract work on the St. Louis Stadium and Convention Center Project. Missouri
Prison Claims analysis, construction oversight, contract administration and expert testimony for a surety involved in the mechanical installations on a prison project. Montana
Prison Prepared a request for an equitable contract adjustment to assist an electrical and security contractor obtain a time extension and compensation for delays experienced during the construction of a prison project. New York
Jail Preparation of an expert report regarding disputed change orders, delay, and project management performance on an expansion of a county jail. Colorado
Building Entitlement analysis, damage evaluation and negotiation of change orders related to the construction of a civic center complex which included a library, jail, fire station, and city hall. California
Building Preparation of a contractor's claims for delays, impacts, and cost overruns experienced during construction of a multiunit apartment complex. Colorado
Building Evaluation of a contractor's delay claim as well as the owner's claim against the architect for errors and omissions related to the design and construction of a bio-research facility. Massachusetts
Building Claim preparation services on a Federal Reserve Bank project, including entitlement analysis, preparation of a detailed as-built but-for CPM schedule analysis to determine responsibility for delay time and damages. North Carolina
Building Evaluation of a contractor's claim associated with the installation of a building management system for a new office complex. New Jersey
Building Schedule delay analysis and presentation of expert witness testimony for a general contractor on a commercial building project. Ohio
Fire Stations Preparation of an expert report regarding design changes, delay, contractual responsibilities, and damages involving a dispute between the architect and the general contractor on the design and construction of three new fire stations. Nevada
Building Complex Provided litigation support including an evaluation of a general contractor's claim against its subcontractor for alleged schedule delays and damages related to the construction of a civil engineering complex on an air force base. Montana
Glass Bottle Manufacturing Plant-Materials Handling Project Analysis of a contractor’s delay and loss of productivity claim against a Finnish equipment supplier providing a design build materials handling facility for a glass bottle manufacturing plant. Colorado
Real Estate Development Litigation support services for a $3 million real estate development project. Created as-planned and as-built CPM schedules for delay and acceleration evaluations including extensive analysis of weather delays. Ohio
Dam Preparation of detailed as-planned and as-built schedule analyses for the contractor on a dam. Participated in negotiations between the contractor and the Province of Alberta. Canada
Lock and
Dam
Claims preparation, including schedule delay analysis and damages analysis, for the electrical contractor on two Corps of Engineers' lock and dam projects. Louisiana
Earth-Filled
Dam
Delay/impact analysis and claims preparation support on an earth-filled dam project resulting in a $55 million settlement from the U.S. Bureau of Reclamation. New Mexico
Wharf Damage and schedule analysis and claims preparation on a concrete wharf expansion project. California
Wharf Evaluation of entitlements and preparation of claim analyses for the contractor for a U.S. Coast Guard wharf at the Port of Los Angeles. Analyzed entitlement issues and wrote expert reports. California
Highway Provided CPM scheduling, pay application, and dispute resolution services for the owner of the E-470 Public Toll Road Project. Monitored and tracked the general contractor's 5,500 activity schedule and developed procedures for updates and changes. Colorado
Highway Schedule delay analysis and damages analysis for the general contractor on a highway improvement project. Colorado
Highway Provided contract/entitlement analysis and schedule analysis for construction of an interstate highway. Construction activities analyzed included clearing, grading, cut and fill operations, and concrete work for bridges. Pennsylvania
Highway Preparation of detailed as-planned and as-built schedule analyses for the contractor on a highway construction project in Pennsylvania. Assisted the contractor to prepare a recovery schedule to mitigate construction delays caused by differing site conditions. Pennsylvania
Refinery Analysis of a large engineering and construction firm's claims for cost overruns and delays associated with the lump sum construction of hydrocarbon production and process modules for the Kuparuk project. Alaska
Refinery Analysis of an European/Japanese EPC firm’s $75 million claims on a refinery upgrade project. Assessed the technical entitlement of over 100 change orders forming the basis of the claims as well as the schedule analysis to demonstrate entitlement to an extension of time and delay damages. Evaluated the loss of productivity analysis for proof of damages for labor cost overruns. Belgium
Refinery Claims analysis, damages assessment, and delay evaluations on a major refinery expansion project involving $20 million in damages. The primary issues included bid error, loss of labor productivity, delay and acceleration. California
Refinery Analysis of delays to the start-up and commissioning of an Upgrader Refinery that was built to process synthetic crude oil from a tar sands production facility. The delays were allegedly caused by a fire at the tar sands production mine site, which delayed the transport of bitumen to the refinery through a 200-plus mile pipeline. Canada
Refinery Analysis of the expediting costs associated with the $250 million rebuild of a refinery in Canada following a fire. This work is being performed in support of the insurance company’s interest on a property damage claim filed by the owner of the refinery. Canada
Refinery Analysis of a major fire at a Canadian refinery that processed synthetic crude oil from a tar sands facility. Our client, a major construction company and its insurer, was defending against liability for property damage and business interruption damages amounting to $1 billion. Canada
Refinery Analysis of issues regarding knowledge of delays and cost overruns associated with the issuance of an insurance policy. Canada
Refinery Damages consultant for the owner defending numerous change order claims on an international oil refinery upgrade project. Provided critical assessments of the contractor's pricing of its change order estimates. Canada
Refinery Preparation of an expert report defending against a contractor's claim associated with disputed change orders, delay and loss of productivity on a new refinery debutanizer unit. Colorado
Refinery Analysis of an owner's $19 million claim against a major engineering and construction firm relative to home office and field cost budget overruns under a reimbursable contract for a $200 million refinery project. Illinois
Refinery Analysis and Expert Report regarding design defects that allegedly caused a failure of welds attaching the diplegs to the cyclone body in an FCC regenerator. Texas
Refinery Analysis of a major international contractor's $22 million delay and disruption claim on a $100 million refinery upgrade project involving new hydrotreater and sulfur recovery units. Prepared a detailed schedule delay analysis, damage analysis, and provided mediation testimony. Trinidad
Refinery Analysis of a Canadian contractor's $45 million delay and disruption claim against the owner of a Caribbean refinery involving the construction of a new Visbreaker Unit, revamped Fluid Catalytic Cracking unit, and Instrument Modernization facilities. Trinidad
Refinery Schedule delay and change order analysis in support of an owner's defense of a $10.5 million claim on upgrades to piping, boiler and flare facilities in a major international oil refinery. Trinidad
Refinery Analysis of a contractor's pipe fabrication loss of productivity claim on a project involving the upgrade to an existing refinery. U.S. Virgin Islands
Oil Terminal Project Analysis of a Korean contractor's $75 million delay and disruption claim and the owner's counterclaims due to late and defective work on a major oil terminal project. Asia
Oil Terminal Project Expert report and testimony regarding the analysis of an owner's property damage claim following a fire at an oil terminal. Louisiana
Petrochemical
Plant
Analysis of the quantum aspects of a contractor's $140 million delay and changed conditions claim involving the relocation of a petrochemical plant project site after construction had commenced because of the discovery of unfavorable soil conditions. Prepare expert report, rebuttal expert report, and testified in ICC arbitration. Algeria
Petrochemical
Plant
Analysis of a contractor's $11 million claims involving disputed change order work, loss of productivity, late materials deliveries, and other delay events on a new petrochemical plant project. Angola
Petrochemical
Plant
On behalf of the owner, analysis of the integrity of an EPC contractor's CPM baseline schedule and schedule updates, and a cumulative impact claim on a major petrochemical plant project. Nigeria
Petrochemical
Plant
Analysis of the integrity of a Korean contractor's EPC schedule regarding logic problems, constraints, and reasonable critical path of a major petrochemical plant project. Nigeria
Petrochemical
Plant
Analysis of a $500 million property damage and business interruption claim resulting from fire damage to a petrochemical plant. Costs and schedule analyses were prepared considering acceleration, betterments, upgrades, and non-rebuilt facilities. Texas
Petrochemical
Plant
Analysis of delays and time extension entitlement on a $75 million claim involving the engineering, procurement, and construction of a major petrochemical plant. Texas
Petrochemical Plant Site Relocation Prepared an expert report and testified in ICC arbitration regarding the heavy civil construction cost increases associated with relocating a petrochemical plant site after construction has started as a result of undesirable soil conditions that were discovered during the project. Algeria
Polypropylene Petrochemical Plant Analysis of a contractor's delay and loss of productivity claim on the design and construction of a polypropylene project. Argentina
Ethylene
Plant
Analysis of delays, acceleration, change orders, unit rate, and loss of productivity claims totaling $20 million by a major U.S. engineering contractor and counterclaims by a major U.S. chemical company on an ethylene plant project. Argentina
Ethylene
Plant
Analysis of delay and acceleration claims on the engineering, procurement, and construction of a ethylene project. Trinidad
Ethylene
Cracker 
Analysis of delay and disruption claims on the engineering, procurement, and construction of a ethylene cracker project. The Netherlands
Chemical
Plant
Preparation of an owner's claim against an engineering & construction management firm who was defaulted for defective design, delays, and cost overruns on a guaranteed maximum price contract to build a commercial-scale chemical plant scaled up from a pilot plant test facility. Colorado
Chemical
Plant
Entitlement and schedule analyses and damage evaluation for a contractor's $12 million claim against a major international chemical company related to the construction of two process units in an existing chemical plant. Louisiana
Chemical
Plant
Analysis of an EPC contractor's change order and delay claims on a chemical plant project. Louisiana
Chemical
Plant
Analysis of an owner’s claim for delays and cost overruns against the engineering, procurement, and construction contractor of a polyol chemical plant project. Tennessee
Chemical
Plant
Analysis of a contractor's claim for change orders, delay, and disruption on a chemical plant in Texas involving issues of contract interpretation of whether the contract was reimbursable or unit rate/lump sum price. Texas
Chemical
Plant
Analysis of the delays associated with the punchlist work, mechanical completion, and startup/commissioning of a chemical plant in The Netherlands. The Netherlands
Condensate Plant Evaluation of an owner's errors and omissions claim against the design contractor on a condensate plant project. Colorado
Fiberglass Insulation Plant Expert report involving the analysis of an owner's claim against the EPC contractor involving defective work, overcharging, delay, and unjustified increased costs associated with the design and construction of an expansion to an existing fiberglass insulation manufacturing plant. Canada
PET Chemical
Plant
Analysis of an engineering & construction contractor’s $154 million change order, delay, and disruption claim against the owner of three PET chemical plants. This project involved ICC arbitration over the terms of a lump-sum turnkey contract and a program agreement for multiple projects. The scope of work included the organization and coding of thousands of documents into an internet-based document retrieval system and assessments of alleged delays and disruption impacts identified in change orders, field change requests, correspondence, meeting minutes, disruption notices, monthly progress reports, and CPM updates. Spain, Argentina, and The Netherlands
Linear Alpha Olefin (LAO) Project Analysis of an EPC contractor’s change order, delay, and loss of productivity claims on a Linear Alpha Olefin (LAO) Project. Canada
LNG Facility Analysis of the adequacy of a cost estimate and construction risks associated with the upgrade of an LNG facility. Trinidad
LPG FPSO
Project
Analysis of a Japanese contractor’s $35 million change order, delay, and loss of productivity claims on a LPG FPSO project being constructed in Japan for installation in West Africa. Japan/West Africa
Magnesium
Oxide Plant
Analysis of the technical entitlement of over 400 change orders associated with an engineering and construction contractor’s $60 million claim on a magnesium oxide production plant. Determined the cause-effect relationship between the changed work and the resulting schedule impact and additional costs. Work is in preparation for expert testimony at an ICC arbitration hearing. Jordan
MTBE Plant Analysis and expert report/testimony regarding an owner's alleged business interruption loss due to an unplanned shutdown of an MTBE plant. Canada
Nitrogen
Plant
Analysis and Expert Report in support of the owner’s entitlement to claims against the EPC contractor involving the standard of care in its management of the design and construction of a nitrogen plant project. Mexico
Offshore Oil Production Facility Analysis of a $45 million delay and disruption claim by a South African contractor involving the engineering, fabrication, and erection of two oil production facilities for a major U.S. oil company. Africa
Offshore and Onshore Gas Production Facility On behalf of the Owner, performed an analysis of defective design and fabrication work on an offshore and onshore gas production facility. Testified in arbitration. Australia
Offshore Oil Production Facilities On behalf of the Owner, assessed fabrication defects on two offshore oil production facilities. Developed the supporting cost documentation to establish to quantum for the owner's claim. Gulf of Mexico
Offshore Oil Production Facility On behalf of the Owner, performed an analysis of a mechanical contractor's $7 million marine lien delay and disruption claim against a major oil company on an offshore oil production project. The claim involved the value of equipment, piping, and structural installations on two refurbished rigs. Nigeria
Offshore Oil Production Facility On behalf of the Owner, performed an evaluation of cost and schedule overruns for the fabrication of two offshore oil and gas production facilities in South Korea. The project involved modular production platforms and structure support structures that were transported for hookup off the coast of Angola. South Korea/ Angola
Offshore Oil & Gas Production Facility Analysis of change order and delay claims totaling $85 million submitted by a South Korean EPC contractor on the construction of an offshore production facility. South Korea and Texas
Offshore Oil & Gas Production Facility Analysis of a contractor's claim for delay and disruption allegedly resulting from work associated with removal of lead-containing paint from the process plant modules and platforms of an offshore oil production facility. Texas
Offshore Oil & Gas Production Facility On behalf of the Owner, performed an analysis of cost overrun claims resulting from mismanagement, delays, and rework by an EPC contractor for an offshore oil and gas production SPAR installed in the Gulf of Mexico. Texas and Finland
Offshore Spar Production Facility Analysis in support of an Owner's claim against an international EPC contractor's performance, delays, and $160 million cost overrun regarding a Spar production facility installed in the Gulf of Mexico. Issues involve material delays, welding rework, quadrupling of labor man-hours, wet mating of hard and soft tank/truss, delay, liquidated damages, conversion of contract issues, and related damages. Finland, Texas, and Gulf of Mexico
Offshore Spar Production Facility Analysis of a contractor's claim for delay and disruption allegedly resulting from work associated with removal of lead-containing paint from the process plant modules and platforms of an offshore oil production facility. This project also involves the defense against the Owner's delay claim for recovery of lost profits due to the delay allegedly caused by the lead abatement program. Texas and Gulf of Mexico
Offshore
Drilling Rig
Analysis of contractual responsibilities for cost overruns and delays on the fabrication of components of an offshore drilling rig. Texas
Crude Oil FPSO Project On behalf of the Owner, assessed a contractor's claim for change orders, delays, and acceleration regarding the design and fabrication of an deep-sea crude oil FPSO project. Assessed the reasonableness of the contractor's baseline and updated schedules, and determined potential delays caused by delivery of design information from other components of the project. Brazil
Semi-Submersible Deepwater Hull and Mooring System Oil Production Facility On behalf of the Owner, evaluated a contractor's $50 million delay and disruption/loss of productivity claim resulting from alleged design changes to a semi-submersible hull and mooring system project. Norway and Gulf of Mexico
Oil Shale
Project
Development of cash flow economic evaluation computer models and preparation of capital and operating cost estimates and economic analyses used in the negotiation of the $1.1 billion project loan guarantee for the Colony Shale Oil Project. Colorado
CO2 Recovery Process Plant Claims analysis and preparation of a damages and schedule analyses in support of the owner's defense against a contractor's $5 million delay and disruption claim on a fast-track CO2 recovery process plant facility. Texas
Coke Gasification Plant Analysis of alleged deficiencies in the design of a petroleum coke gasification and syngas plant, resulting in change orders, delay, and loss of productivity claims totaling $25 million against the owner of a refinery. Kansas
Delayed
Coker
Preparation of a mechanical contractor’s $20 million claim for delay, additional work, labor disputes, and loss of productivity regarding a delayed coker project at the Cerro Negro oil upgrading project. Assisted counsel in the preparation of its briefs and document discovery requests, and prepared an expert report which was intended for witness testimony at ICC arbitration hearings in Geneva, Switzerland; however, the case settled before the hearing was conducted. Venezuela
Coal Gasification
Plant
Litigation support, database management system development, and assessment of the technical design, cost and schedule overruns, and start-up problems of a coal gasification project. Alabama
Fertilizer Plant Claims preparation, database development and analysis of costs and schedules for a $450 million fertilizer plant. Prepared a $100 million claim against the owner, which was abandoned as a result of the Gulf War. Successfully negotiated one Turkish and two Korean subcontractor's claims against the Japanese prime contractor. Iraq
Soybean Processing Plant Preparation of a contractor's delay and loss of productivity claim against an owner cooperative on the construction of a $32 million soybean processing plant. South Dakota
Blast Furnace / Coke Oven Litigation support of a $400 million blast furnace and coke oven battery project involving analysis of construction cost and schedule overruns and the adequacy of the engineering design. Indiana
Gas Processing Plant Claims analysis, entitlement analysis, schedule analysis and assessment of $20 million in cost overruns on a lump sum, fast-track gas processing plant project. Issues included defective specifications, changes, and delays. California
Gas Plant Analysis of schedule delays and increased costs associated with an EPC contractor's $125 million claim on a gas plant project. Saudi Arabia
Gas Turbine Generators equipment by the turbine/generator manufacturer on a new power plant project. The schedule analysis also supported the contractor's defense of liquidated damages assessed by the owner because of delays caused by the turbine/generator manufacturer. Colorado
Gas Turbine Generators Analysis of delays, acceleration, and loss of productivity impacts caused by numerous change orders, late delivery of materials and equipment by the turbine/generator manufacturer, and inadequate and untimely responses to requests for information on a new power plant project. This project involves the preparation of a request for equitable contract adjustment to support the contractor's $40 million claim. Texas
Gas Compressor/ Pipeline Project Analysis of delay and performance problems on a gas compressor/pipeline project resulting in liquidated damages in excess of $50 million. This project involved ICC arbitration in Geneva, Switzerland. India
Pipeline Compressor Station Project On behalf of the owner, analysis of an EPC contractor's $43 million claim involving alleged P&ID changes to the FEED design of a compressor station and pipeline project, and resulting delay to the completion of the project. Nigeria
Oil & Gas Gathering Center Facilities Analysis of delay and disruption impacts incurred by a construction company on revamp of an oil and gas gathering center. The project involved extension of and tie-ins to large diameter, high pressure crude oil headers and collection pipelines Kuwait
Gas Compression and Wellhead Offshore Platforms Analysis and testimony supporting a major oil company’s claim against a contractor for $29 million in improper charges on a reimbursable contract for the fabrication of one offshore gas compression platform and two wellhead platforms. Louisiana and Venezuela
Gas Turbine Generators Analysis of delays and loss of productivity impacts caused by late delivery of equipment by the turbine/generator manufacturer on a new power plant project. The schedule analysis also supported the contractor's defense of liquidated damages assessed by the owner because of delays caused by the turbine/generator manufacturer. Colorado
Gas Turbine Generators Analysis of delays, acceleration, and loss of productivity impacts caused by numerous change orders, late delivery of materials and equipment by the turbine/generator manufacturer, and inadequate and untimely responses to requests for information on a new power plant project. This project involves the preparation of a request for equitable contract adjustment to support the contractor's $40 million claim. Texas
Natural Gas
Pipeline Project
Analysis of a French contractor's $14 million claim on a gas pipeline and valve station project. Trinidad
Pipelines Analysis of delay and disruption claims by a French contractor on the construction of a natural gas pipeline and valve station project. Trinidad
Nuclear
Power Plant
Prudency audit of a large nuclear power plant including the evaluation of the justification and causes for scope and cost growth as well as the origin, components and reasonableness of $1.3 billion of start-up and commissioning cost overruns. Arizona
Nuclear
Power Plant
Litigation support of a nuclear power plant project involving assessment of cost overruns, delays, inadequate QA/QC documentation, and defective electrical and instrumentation installations. Louisiana
Nuclear
Power Plant
Analysis of schedule delay, productivity loss, and direct damages totaling over $1 billion allegedly resulting from problems related to hydrodynamic loads on a nuclear power plant reactor building. Ohio
Geothermal
Power Plant
Damage and schedule analysis and claims assistance for the electrical and instrumentation contractor on a geothermal power plant project. California
Geothermal
Power Plant
Evaluation of the integrity of a contractor's schedule and analysis of delay and loss of productivity claims associated with the design and construction of a new geothermal power plant project. Indonesia
Cattle Manure & Biomass Power Plants Analysis of operating performance problems and cost overruns for the lending bank on a cattle manure-fueled power plant and several agricultural waste-fueled power plants. California
Hydroelectric Power Plant Project Preparation of a claim on the assembly of turbine generators on a hydroelectric power plant project. Colorado
Hydroelectric Pumped Storage Facility Preparation of entitlement and damage analyses for a hydroelectric pumped storage facility in South Carolina. Performed financial analyses and wrote expert reports. South Carolina
Coal Fired
Power Plant
Preparation of a $1.0 million claim involving the installation of new Low NOx and boiler reheater facilities on a power plant project. Indianapolis
Coal Fired Power Plant Analysis of a major mechanical contractor's $11 million claim against an engineering and construction contractor involving the installation of new pollution control equipment on a power plant project. Tennessee
Gas-fired Power Plant and Heat Recovery Steam Generators Analysis of change orders, delays, acceleration, and loss of productivity impacts associated with the relocation of an existing gas-fired turbine generator and the construction of a new heat recovery steam generator in an existing industrial plant. This project involves the defense against the contractor's claim and preparation of the owner's liquidated damages counterclaims. Alaska
Gas-fired Power Plant and Heat Recovery Steam Generators Analysis of EPC contractor’s $40 million claim regarding a lump-sum contract to design and build a gas-fired power plant. Assessed the EPC contractor’s allegations regarding the constructibility of the heat recovery steam generators and the delay and disruption impact of those problems on its work. Illinois
Heat Recovery
Steam Generation
Analysis of the HRSG manufacturer's responsibility and liability for delays, scope of work changes related to increased piping quantities, and backcharges from the general contractor on the installation of four waste heat recovery steam generators. California
Heat Recovery
Steam Generation
Analysis of contractor's claim for delay, acceleration, scope of work changes, and loss of productivity on the installation of three waste heat recovery steam generators. Louisiana
Wastewater Analysis of contractors' claims against the owners of wastewater treatment plant projects. Issues involved include delay, changes, defective specifications, and loss of productivity. Ohio, Alaska, and New Mexico
Industrial Wastewater Treatment  Analysis of a delay and disruption claim on an industrial waste water treatment plant project Trinidad
Subway Quality control and reasonableness review of a schedule delay analysis for a tunnel-boring contract on the Los Angeles metro subway project. California
Subway Analysis of issues and schedule delays associated with the design and installation of new communications systems on the London Underground subway system. England
Light Rail Preparation of monthly progress reports and schedule updates for the preliminary engineering and final civil design of the $600 million Central Florida Light Rail Transit System in Orlando, Florida. Developed detailed civil design, construction and system-wide interface schedules. Florida
Transit Financial and schedule audits for the Los Angeles County Transportation Commission on light rail and metro subway projects. Reviewed project budgets, contractor schedules, construction manager monthly progress reports, and advised the County of potential cost overruns, schedule delays and reporting deficiencies. California
Transit Pricing and negotiation of change orders for the Bay Area Rapid Transit District on a $65 million train control contract. Evaluated entitlement, prepared schedule analyses, wrote findings of fact, and negotiated change orders. California

 