Gas, GTL, LNG, and NGL Plants
Long International personnel have been involved in numerous claims and project consulting assignments associated with gas, gas-to-liquids (GTL), liquified natural gas (LNG), and natural gas liquids (NGL) plants. Many of these projects have been located outside the United States.
Please contact us for additional information.
Gas Plants-
Algeria On behalf of the owner, performed an analysis of the quantum aspects of a contractor's $130 million delay and changed conditions claim involving the relocation of a $700 million natural gas processing plant project site after construction had commenced because of the discovery of unfavorable soil conditions. The owner counterclaimed delay damages because the plant was completed late. Issues involved alleged increased quantities for earthworks and pipelines in the new site location, subcontract labor man-hours and costs, engineering and construction management man-hours and costs, and associated delay, productivity loss, and other costs, and whether the contractor had sufficient documentation to support its claims. The owner alleged bid error by the contractor and inadequate and incorrect quantum calculations to support its claimed costs. Supported the preparation of an expert report and rebuttal expert report, which were submitted in ICC arbitration in Paris, France. The owner received a favorable award at arbitration. Algeria Provided oversight of contractor’s performance during construction phase of a $750 million gas development project. Scope of project included a one bcfd gas plant, 100 kilometers of 12”-24” high pressure gas gathering pipelines, 110 kilometers of 36” sales gas pipelines, 110 kilometers of 12” LPG pipeline and a 120 kilometers of condensate liquid pipeline. Prior to project approval, defined the infrastructure scope of work and the evaluation and clarification of competitive lump-sum bids. owners increased plant capacity requirement by 50% after the initial bids had been submitted which significantly complicated the final scope of work definition and final bid basis confirmation. Australia On behalf of the contractor, evaluated defective design and project management performance problems associated with an offshore underwater gas extraction facility and offshore pipelines, and an onshore gas processing plant. The contractor was a joint venture of the design firm and the underwater pipeline installation company. Under an LSTK Contract, the contractor was responsible for carrying out the design, engineering, procurement, construction and commissioning of the project. The owner terminated the contractor and sought recovery of damages. California Provided claims analysis, entitlement analysis, schedule analysis and assessment of $20 million in cost overruns on a lump sum, fast-track gas processing plant project. Issues included defective specifications, changes, and delays. Canada Provided claims analysis services for the insurance company regarding the reconstruction of a natural gas plant in British Columbia following an explosion. Performed a schedule analysis to determine when the reconstruction of the plant could have been completed absent the improvements to the facility made by the owner. Colorado Managed design, contracting and construction of the $18 million relocation of a 100 mmcfd cryogenic gas plant from Platteville, Colorado to the Texas Panhandle, installation of 5-miles of 12” sales gas pipeline and a $20 million wellhead automation project. Managed all aspects of the project, including preparation, execution and administration of engineering and construction contracts, procurement of major equipment, cost and schedule control and invoicing / asset allocation accounting. Gulf Of Mexico Provision of claims support and ad-hoc contract administration, including some bid document preparation for a contractor on a gas receiving station. Kansas Provided expert witness testimony for a royalty owner / producer dispute regarding post-production expenses associated with the Kansas-Hugoton gas field. Nigeria Provided schedule quality assurance services regarding a Gas Supply Expansion Project. Evaluated schedule metrics and appropriateness of the critical path of the baseline schedule. Saudi Arabia On behalf of the owner, performed analyses and prepared expert reports regarding schedule delays and increased costs associated with an EPC contractor's $138 million claim on a gas plant expansion project. The work involved correction of the contractor's baseline schedule and schedule updates, assessment of impacts allegedly due to change orders, welding defects, late delivery of drawings by the owner, and contractor performance problems. Prepared time impact and as-built but-for schedule analyses to address time extension entitlement, compensable delay, and loss of productivity. Developed a chronological database and assisted the law firm with witness statements and document disclosure requests. Completed a comparative assessment between the project’s radiography records for the rejected pipe joint welds, and the results that were developed from the owner’s Radiography Expert’s interpretation of the films. Evaluated the opposing experts' schedule delay and damages analyses and assessment of responsibilities for project management performance problems. The dispute was resolved prior to arbitration. Trinidad Evaluated the owner's project management and cost and schedule control procedures for performing major capital projects. Prepared stage gate project development procedures, and developed cost and schedule control procedures. Trinidad Assisted with the development of a Project Management Controls Unit for a natural gas company. Prepared written findings and recommendations for establishing a Project Management Controls Unit and developing a Project Management Methodology. United Arab Emirates Contract and commercial support during negotiation meetings with a U.S. supplier who may have supplied defective equipment. All discussions were subject to a detailed root cause analysis and material testing. Wyoming Performed the preliminary process design for the acid gas removal and condensate stabilizer units for a new sour gas plant located in the remote mountains near Evanston. Managed EPC contractor through engineering design and on-site during construction of this $250 million cost reimbursable project.
Gas-to-Liquids (GTL) Facilities-
Germany, Nigeria Evaluation of a civil subcontractor's delay claim regarding foundation and civil works associated with a Gas-to-Liquids facility. Evaluated the integrity of the subcontractor's schedules and verified the impact of changes to the subcontractor's schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor's claim. Nigeria On behalf of the owner, performed an analysis of the EPC contractor's schedules for a multi-billion Gas-to-Liquids facility. Verified the schedule work scope against contract requirements. Evaluated schedule metrics, reviewed schedule logic, assessed the reasonableness of the critical path and provided recommendations for optimizing the schedule. Also evaluated a cumulative impact claim. Nigeria Evaluation of a piping module subcontractor's delay claim associated with a Gas-to-Liquids facility. Evaluated the integrity of the subcontractor's schedules and verified the impact of changes to the subcontractor's schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor's claim. Trinidad Performed project management audits of a Gas-to-Liquids facility to assist with evaluating the outstanding engineering and construction scope, assess restructuring of the Project Management Team, and assist with the development of a Request for Proposal for the selection of a Project Management contractor. Trinidad On behalf of the Receiver in a bankruptcy proceeding, performed project management audits of a Gas-to-Liquids facility to assist with evaluating the outstanding engineering and construction scope, assess restructuring of the Project Management Team, and assist with the development of a Request for Proposal for the selection of a Project Management contractor.
Liquified Natural Gas (LNG) Plants-
Angola Analysis of EPC schedules for a $2.7 billion LNG facility. Verified the schedule work scope against contract requirements. Evaluated schedule metrics, reviewed schedule logic, and assessed the reasonableness of the critical path. Angola On behalf of the owner, analyzed schedule delay claims by the prime contractor on an LNG facility being constructed. Australia Contract awareness services on an LNG Development Project. Carried out detail review of all contract agreements (FEED, LOA & Subcontractor). Prepared “Contract Obligations Matrix” and delivered “Contract Awareness Workshops.” Canada On behalf of an insurance company, performed an analysis of delays to the construction of an LNG terminal in New Brunswick, including equipment to unload tanker, transfer to LNG storage tanks, vaporize the LNG, and meter the gas as it is introduced into the natural gas pipeline. The claim was filed by the owner as a result of materials being lost overboard at sea in severe weather while being shipped to the site. Indonesia Managed fast-track temporary facilities, technical trials and final design scope through front-end engineering design, cost and schedule of a $40 million LNG Plant waste water treatment facility in West Papua. The need for special waste water treatment equipment was not discovered until start-up of the new LNG facility. Therefore, defining the scope (treatment chemistry and equipment), logistics issues to West Papua and maneuvering through the government technical and procurement approval processes had to be managed on a fast-track in order to allow the LNG plant to start-up and continue operations. Indonesia Managed owner’s multi-discipline team and third-party engineering contractor from concept through front-end engineering design, cost and schedule scope definition of a $2 billion development of offshore gas reservoirs and associated platform and pipeline facilities and the expansion of onshore facilities, including a third, 3.8 million tonne per annum LNG train in West Papua. Italy, Spain Performed an analysis of delays and project management performance deficiencies in defense of a $40 million claim of an EPC contractor for additional overhead and fee on a cost reimbursable contract for the management of the design and construction of an LNG Terminal Project that was delayed over 18 months. Analyzed deficiencies in the EPC contractor's schedules, and performed an analysis of concurrent delays. Prepared the basis of a counterclaim by the owner against the EPC contractor. Mexico The project involved the EPC construction of a green field LNG terminal including major berthing facilities and on-shore storage, processing, and pumping services. Provided lead contract and claims support to the EPC contractor Joint Venture to ensure recovery of owner caused impacts throughout the construction process. This involved managing and defending a major claim from the international earthworks subcontractor through litigation proceedings in both the U.S. and Mexico. This involved detailed rebuttal of schedule, disruption, and damages analyses. Nigeria Developed the implementation of a contracting strategy for 10 MM TPY grass roots LNG liquefaction plant. Assignment included preparation of bid packages and bid evaluations for 8 LSTK contracts that covered every portion of the project. Facilitated senior shareholder meetings to arrive at the strategy and to approve its implementation. Singapore, Spain On behalf of the owner, performed an analysis of a $15 million cost overrun and cumulative effect claim by an electrical subcontractor on an electrical and instrumentation building to be installed offshore on an LNG facility. The subcontractor alleged increased complexity of the work, loss of productivity and delays associated with changes to its scope of work, and subsequent acceleration. The owner alleged that the changes did not cause the alleged quantum sought by the subcontractor, and that the subcontractor underbid the work and mismanaged its resources. Trinidad Performed an analysis of the adequacy of a cost estimate and construction risks associated with the upgrade of an LNG facility.
Natural Gas Liquids (NGL) Plants-
Illinois Retained by the owner of a natural gas liquids extraction and fractionation plant involved in arbitration with the electrical and instrumentation contractor. Analysis and opinions provided included contract review, determination of breach of contract, delay analysis, and calculation of cost reimbursements owed to the contractor and damages incurred by the owner. Illinois Analyzed damages for an owner regarding the cost reimbursable construction of a large NGL separation, processing and storage facility. Damages analysis focused on the reasonableness and causation of significant construction and startup cost overruns related to work performed by the prime contractor’s electrical subcontractor. Venezuela Prepared CPM fragnets depicting schedule delays and analysis of productivity losses on a natural gas liquefaction project. Wyoming Provided analysis regarding schedule delay and cost overrun issues on a NGL processing project involving construction of central process and satellite facilities. The analysis work was performed on behalf of the owner to identify the magnitude and compensability of potential affirmative claims against the prime contractor.