Developed a contractor’s $21 million delay and disruption claim against the owner of a 4×2 combined cycle power plant in Romoland. The scope of work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

California

Developed a contractor’s $21 million delay and disruption claim against the owner of a 4x2 combined cycle power plant in Romoland. The scope of work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

New Jersey

Performed schedule delay and damages analyses and prepared an expert report for a subcontractor performing the cooling tower design and construction on a combined cycle power plant project.

Power

New Jersey

Assisted a mechanical contractor in a $7 million dispute with an EPC contractor over additional costs associated with delays, disruptions and loss of productivity on a 300 MW combined cycle power plant. Disputed items included: 1) changes in the scope of work, 2) late delivery of EPC contractor-supplied materials and equipment, and 3) late delivery of necessary design information.

Power

New York

Analyzed a contractor’s delay and disruption claim against the owner of a 4x2 combined cycle power plant in Athens. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

New York

Provided scheduling support to an estimating team on a $250 million 500 MW power plant project. Developed a pre bid schedule over a 12-month period and multiple proposals through contract award. This project required extensive analysis including resource leveling through the use of resource histograms.

Power

California

On behalf of an owner, furnished CPM scheduling services for a 2x1 combined cycle power plant in San Jose.

Power

Pennsylvania

Analyzed a contractor’s $8 million delay and disruption claim against the owner of a 2x1 combined cycle power plant in Redding. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

Indonesia

Prepared the detailed schedule for a multi-block combined cycle conversion project.

Power

Pennsylvania

Analyzed a contractor’s delay and disruption claim against the owner of a 3x1 combined cycle power plant in Philadelphia. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

Texas

Analyzed a contractor’s $8 million delay and disruption claim against the owner of a 4x2 combined cycle power plant in Fairfield. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.