On behalf of an engineering design and project management firm of a fuel oil and diesel oil bulk storage tank farm facility, evaluated and rebutted claims by the owner regarding alleged delays, loss of revenue, repair costs, and cost overruns caused by errors and omissions in design and negligence that hampered the safe and profitable operation of the storage facility. Prepared an expert report for submission to the Appeals Circuit at the Commercial Court of Jeddah, Saudi Arabia, rebutting the engineering design and project management firm-caused design errors, omissions, and delays.

Refineries, Petrochemical, and Chemical

Saudi Arabia

On behalf of an engineering design and project management firm of a fuel oil and diesel oil bulk storage tank farm facility, evaluated and rebutted claims by the owner regarding alleged delays, loss of revenue, repair costs, and cost overruns caused by errors and omissions in design and negligence that hampered the safe and profitable operation of the storage facility. Prepared an expert report for submission to the Appeals Circuit at the Commercial Court of Jeddah, Saudi Arabia, rebutting the engineering design and project management firm-caused design errors, omissions, and delays.

Power

Finland

On behalf of an owner, evaluated a contractor’s expert report and €18 million delay and disruption claim concerning the replacement of emergency diesel generators on a nuclear power plant in Finland. Assessed the expert’s time extension analysis, which was found to lack an assessment of the critical path of the work. The claim was ultimately rejected.

Power

Finland

On behalf of an owner, prepared and evaluated claims concerning the design and construction of one of Europe’s largest nuclear reactor and turbine generator facilities, involving multiple tranches of claims submitted over the course of several years. Conducted schedule delay and quantum analyses on approximately €3.6 billion in contractor claims and approximately €2 billion of owner counterclaims. Reviewed the merits of outstanding change orders that were part of the contractors’ claims. Assessed claims associated with loss of productivity, time-related costs, subcontractor pass-through costs, delayed and disputed payments, overhead, profit, and interest. Provided expert testimony concerning delays and quantum during arbitration proceedings held at the International Chamber of Commerce.

Power

Saudi Arabia

On behalf of an EPCM contractor for the construction of two coal/oil-fired power plant projects in Saudi Arabia, provided claim support services concerning the owner’s denial of payment of final invoices and other costs associated with the EPCM contractor’s consulting works. The owner alleged that the EPCM contractor did not deliver technical documents such as plans, engineering drawings, computer network support services, and additional engineering support services. Supported the legal team’s preparation of the Statement of Claim submitted to the Riyadh Commercial Court concerning the EPCM contractor’s entitlement to additional payment. The court awarded a very favorable settlement to the EPCM contractor.

Power

Saudi Arabia

On behalf of one of the consortium contractors, evaluated claims against the other consortium contractor associated with a power and desalination project in the Middle East. The power plant design involved a change from a sub-critical power block to high-efficiency super critical technology. Evaluated numerous claims involving disputed variation orders involving technical design, equipment supply, and construction issues, delay, and increased costs. Prepared an expert report in arbitration. Provided direct and cross-examination testimony at the arbitration hearings in Dubai, UAE.

Refineries, Petrochemical, and Chemical

Alberta, Canada

On behalf of an EPC contractor, analyzed change order, delay, and loss of productivity claims on a linear alpha olefin project.

Mining and Mineral Processing

Mexico

Provided claims prevention training seminars for a mineral processing engineering firm in Denver, Tucson, and Mexico City. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.

Power

Singapore

The project centered on disputes between a major contractor and a mechanical/electrical subcontractor on alleged delay and disruption impacts during the construction of a 380 MW power facility due to alleged late information, delayed procurement, and changes. Project completion was significantly delayed, and the subcontractor claimed the contractor caused the negative schedule impacts, subsequently submitting a request for an equitable adjustment (REA) and filing for arbitration. Team leader engaged to consult on the main contractor’s defense of the claim both during the contract execution works and the post completion arbitration events. This involved day-to-day contract administration, claims preparation, and overall management of claims team, outside counsel, and experts.

Gas, Gasification, GTL, LNG, and NGL

Mexico

The project involved the EPC of a greenfield LNG terminal including major berthing facilities and onshore storage, processing, and pumping services. Provided lead contract and claims support to the joint venture EPC contractor to ensure recovery of owner-caused impacts throughout the construction process. This involved managing and defending a major claim from the international earthworks subcontractor through litigation proceedings in both the U.S. and Mexico. The scope of work further involved detailed rebuttal of schedule, disruption, and damages analyses.

Power

United Kingdom

On behalf of a government controlled nuclear management company, performed a third-party review and upgrade analyses of its bidding processes and contract conditions for the decommissioning and new construction of nuclear power plants. Reviewed the contract/bidding documents and provided an independent risk management report covering best practices, PMBOK application, project success goals, and general procedures for upgrading contractor performance.

CONTACT US

Experience Matters

Our experts are ready to help.

Long International 25th Anniversary Logo

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.