A hospital facility was badly damaged during a major hurricane. Provided full insurance claim review services. Worked with claim adjusters to assess and review actual damage and required construction repair services. This involved a full construction assessment of building, services, and medical equipment damages including time/costs and rectification budget for repair and/or total replacement of facility.

Building Construction

Texas

A hospital facility was badly damaged during a major hurricane. Provided full insurance claim review services. Worked with claim adjusters to assess and review actual damage and required construction repair services. This involved a full construction assessment of building, services, and medical equipment damages including time/costs and rectification budget for repair and/or total replacement of facility.

Power

Texas

Assessed the management performance and analyzed cost overruns on the South Texas Nuclear Project. Presented testimony in the prudency hearings conducted by the Texas Utility Commission.

Power

Texas

Analyzed a contractor’s $8 million delay and disruption claim against the owner of a 4x2 combined cycle power plant in Fairfield. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

Texas

Analyzed a contractor’s $22 million delay and disruption claim against the owner of a 3x1 combined cycle power plant in Baytown. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Offshore Oil and Gas

Texas

On behalf of an owner, analyzed a mechanical contractor’s $7 million marine lien delay and disruption claim against a major oil company on an offshore oil production project. The claim involved the value of equipment, piping, and structural installations on two refurbished rigs.

Offshore Oil and Gas

Texas

Defended an oil and gas producer against an $8 million claim from an EPC contractor and shipyard for additional costs alleged to have arisen as a result of a significant increase in scope and project delay. Analysis revealed that defendant had failed to properly consider nearly $8 million in paid extra work. Claim was settled in mediation.

Industrial and Manufacturing

Texas

Assisted a supplier of proprietary equipment in defending against a $20 million claim on a project involving the design, delivery and construction of a new cement production line from ore receiving to clinker storage and loadout. The general contractor claimed for increased costs allegedly due to delays, disruption and labor impact arising from late delivery of design data and proprietary equipment, and a defective design. The case was arbitrated in Texas. The client was found liable for only a portion of disputed extra work.

Refineries, Petrochemical, and Chemical

Texas

Prepared damages and schedule analyses in support of an owner’s defense against a contractor’s $5 million delay and disruption claim on a fast-track CO2 recovery process plant facility.

Refineries, Petrochemical, and Chemical

Texas

On behalf of an owner, analyzed a $500 million property damage and business interruption claim resulting from fire damage to a petrochemical plant. Prepared cost estimates for the property damage claim and schedule analyses considering acceleration, betterments, upgrades, and non-rebuilt facilities.

Building Construction

Texas

Performed schedule delay analysis and damages analysis and prepared an expert report for the electrical and mechanical subcontractors on the Dallas VA Hospital project. Two claim documents were submitted as part of the general contractor’s overall omnibus claim to the VA.