Gas, Gasification, GTL, LNG, and NGL
On behalf of a major international oil company, analyzed the quantum aspects of an EPC contractor’s $130 million delay and changed conditions claim. The claim involved the relocation of a gas processing plant project site after construction had commenced because of the discovery of unfavorable soil conditions. Prepared an expert report and rebuttal expert report and testified in ICC arbitration. The EPC contractor’s claim was denied, and the owner’s liquidated damages claim was upheld.