July 23, 2024
Implied Warranty to Coordinate Other Contractors
Although rarely stated as such in the contract documents, the owner does have a broad series of contractual responsibilities. The owner’s failure to adequately execute these responsibilities can produce a recoverable claim.
This is the third blog post in a series on implied warranties in construction contracts. The first post discusses the implied warranty that plans and specifications are sufficient and adequate for the purpose intended. The second post discusses the implied warranty that neither party to a contract will do anything to prevent, hinder, or delay performance thereof by the other party. The third post discusses the implied warranty that, on multi-prime projects, the owner or construction manager will coordinate the activities of the respective contractors to avoid disruptions.
There exists an implied obligation to supervise and coordinate the work of other contractors and to prevent interferences by such contractors on other contractors. Key terms associated with this issue include failure to coordinate, interference by other contractors, poor project management, congested work areas, stacking of trades, inadequate sequencing of primes, schedule overlaps, restricted access, lack of direction, and held up by others.
This obligation extends from the owner on a multi-prime project, or from the general contractor to its subcontractors. Orderly progress of the work depends on the careful coordination of all prime contractors and subcontractors. Problems arise when sequencing is not carefully planned. Recovering added costs or receiving a time extension depends on whether the owner, the construction manager, or a contractor had the contractual responsibility for coordinating the work.
Personnel should be aware of the problems inherent in coordinating a project. Failure to effectively coordinate may have a “domino effect” on other trades. Voluntary assumption of the responsibility for coordinating, where none exists in the contract, is risky and may expose a contractor to liability.
This warranty to coordinate has been recognized in numerous cases, including:
- Failure to compel cooperation among contractors1
- Failure to prevent deliberate interference from other contractors under the owner’s control2
- Failure to provide jobsite coordination3
- Breaching a contract by failing to expedite work on an adjacent project4
In the case of L.L. Hall Construction Company,5 a dispute arose as to the government’s responsibility to supervise and coordinate other contractors working on the construction site. There, as is found in the typical federal construction contract, the government reserved the right to suspend or change operations. During the project, because of the inefficient operations of two other contractors, the government suspended the plaintiff’s operations and allowed the other work to proceed. The court held that the government had no right to shut down the plaintiff’s efficient operations in favor of the inefficient contractors and that in doing so, it had breached its implied obligation not to delay the blameless contractor. Moreover, the court further held that the government had the affirmative obligation to prevent any interference by the other contractors.
1 Shea-S&M Ball v. Massman-Kiewit-Early, 606 F.2d 1245 (D.C. Cir. 1979).
2 Felhaber Corporation v. New York, 410 N.Y.S. 2d 920, 924, 927 (App. Div. 1978).
3 Forest Electric Corporation v. New York, 275 N.Y.S.2d 917 (Ct. Cl. 1966).
4 Town & Country Eng’g Corp. v. State, 46 N.Y.S.2d 792 (Ct. Cl. 1944).
5 L. L. Hall Construction Company v. United States, 379 F.2d 559, 564 (Ct. Cl. 1966).
ADDITIONAL RESOURCES
Blog
Discover industry insights on construction disputes and claims, project management, risk analysis, and more.
MORE
Articles
Articles by our engineering and construction claims experts cover topics ranging from acceleration to why claims occur.
MORE
Publications
We are committed to sharing industry knowledge through publication of our books and presentations.
MORE
RECOMMENDED READS
Implied Warranty of the Design
This is the first blog post in a three-part series that provides awareness of implied warranties in construction contracts. This post discusses the implied warranty that the plans and specifications are sufficient and adequate for the purpose intended.
READ
Problematic Construction Contract Clauses
This is the first post in a series that discusses construction contract terms that cause difficulties and give rise to claims.
READ
Contract Language: Defining Standard of Care and Good Industry Practice
Language in EPC and EPCM contracts defines standards of care and excellence, good industry practice, and required skills and capacity to perform.
READ