Water, Wastewater, Dams, and Marine
South CarolinaPrepared entitlement and damage analyses for a hydroelectric pumped storage facility. Performed financial analyses and wrote expert reports.
PROJECT EXPERIENCE
Prepared entitlement and damage analyses for a hydroelectric pumped storage facility. Performed financial analyses and wrote expert reports.
An EPC contractor installed a wet type fuel gas desulphurization unit to an existing power facility utilizing combustion turbine scrubbers. The project involved coordination or works around an existing operating plant and a tight site with regard to construction and storage space facilities. Prepared defense for the main contractor from subcontractor and critical vendor supplier claims involving delay and disruption impacts and the application of liquidated damages. The project also suffered from prime contract delays caused by owner interference and local labor regulations and rules instigated by the owner post contract execution that severely impacted the main contractor’s ability to manage the subcontract craft workers. Provided CPM schedule, cost, and change order analyses to support the main contractor’s claims against the owner.
On behalf of an owner, analyzed change order claims alleged by an EPC contractor on an ethanol from corn project at an old brewery site.
Analyzed a $50 million delayed start-up claim on a 500 MW power plant. Evaluated project delays and cost impacts related to the Heat Recovery Steam Generator (HRSG) collapse.
On behalf of the owner of a large petrochemical complex in Louisiana, assessed a scaffolding subcontractor's claim for increased costs on a unit price subcontract where it installed more scaffolding quantities than originally planned and during a longer period due to project delays. Prepared an expert report.
Prepared an extension of time claim for a Japanese contractor. The claim related to the construction of civil, structural, and building design work on a chemical plant project in the UK. Late access to the site and additional and modified work impacted the contractor’s execution of the work.
On behalf of an owner, evaluated outstanding contractual payments, unresolved change orders, and alleged delay costs alleged by a contractor for the fabrication, transportation, and installation of Pipeline End Terminations and Jumpers for an offshore oil production facility.
Analyzed a contractor’s $22 million delay and disruption claim against the owner of a 3x1 combined cycle power plant in Baytown. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.
On behalf of an owner, analyzed the EPC schedules for a $2.7 billion LNG facility. Verified the schedule work scope against contract requirements. Evaluated schedule metrics, reviewed schedule logic, and assessed critical path reasonableness.
Furnished CPM scheduling services for an electrical subcontractor on the $66 million McCormick Place Convention Center expansion project in Chicago. Worked with the subcontractor’s field staff to develop and monitor a resource-loaded completion schedule that tracked the remaining electrical activities. Updated schedules with job cost and certified payroll information. Correctly calculated the critical path on the electrical work and analyzed impacts from other contractors. Performed productivity studies and provided resource and cost projections used for cash flow and cost-to-complete purposes. Assisted the onsite project management team in the successful closeout of the project.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.