Archive

Defended an oil and gas producer against an $8 million claim from an EPC contractor and shipyard for additional costs alleged to have arisen as a result of a significant increase in scope and project delay. Analysis revealed that defendant had failed to properly consider nearly $8 million in paid extra work. Claim was settled in mediation.

Offshore Oil and Gas

Texas

Defended an oil and gas producer against an $8 million claim from an EPC contractor and shipyard for additional costs alleged to have arisen as a result of a significant increase in scope and project delay. Analysis revealed that defendant had failed to properly consider nearly $8 million in paid extra work. Claim was settled in mediation.

Offshore Oil and Gas

Texas

On behalf of an owner, analyzed a mechanical contractor’s $7 million marine lien delay and disruption claim against a major oil company on an offshore oil production project. The claim involved the value of equipment, piping, and structural installations on two refurbished rigs.

Offshore Oil and Gas

Nigeria

On behalf of an owner, analyzed a mechanical contractor’s $7 million marine lien delay and disruption claim against a major oil company on an offshore oil production project. The claim involved the value of equipment, piping, and structural installations on two refurbished rigs.

Offshore Oil and Gas

Texas

On behalf of an owner, analyzed an $85 million change order and delay claim regarding an offshore Compliant Piled Tower constructed in Texas and topsides facilities fabricated in South Korea for installation offshore Angola.

Offshore Oil and Gas

South Korea, Angola

On behalf of an owner, analyzed an $85 million change order and delay claim regarding an offshore Compliant Piled Tower constructed in Texas and topsides facilities fabricated in South Korea for installation offshore Angola.

Offshore Oil and Gas

Gulf of Mexico

On behalf of a paint manufacturer, prepared an expert report refuting an EPC contractor’s claim for delay and disruption allegedly resulting from work associated with removal of lead-containing paint from the process plant modules and platforms of an offshore oil production facility installed in the Gulf of Mexico. Case settled prior to trial. The project also involved the defense against the owner’s delay claim for recovery of lost profits due to the delay to the achievement of first oil allegedly caused by the lead abatement program. Presented an expert report demonstrating that the project would have been delayed because of concurrent delay by the EPC contractor. Testified in deposition, which resulted in a successful settlement of the dispute.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.