Archive

On behalf of a piping manufacturer, analyzed the fabrication of piping components as an element of the fabrication and erection of HRSGs including the identification of aspects of the delay resulting from the actions of the various parties included in the project. Prepared an expert report, which led to settlement of the matter.

Power

Thailand

On behalf of a piping manufacturer, analyzed the fabrication of piping components as an element of the fabrication and erection of HRSGs including the identification of aspects of the delay resulting from the actions of the various parties included in the project. Prepared an expert report, which led to settlement of the matter.

Power

Florida

On behalf of a piping manufacturer, analyzed the fabrication of piping components as an element of the fabrication and erection of HRSGs including the identification of aspects of the delay resulting from the actions of the various parties included in the project. Prepared an expert report, which led to settlement of the matter.

Power

Louisiana

On behalf of a manufacturer of HRSGs, analyzed a contractor’s claim for delay, acceleration, scope of work changes, and loss of productivity on the installation of three waste HRSGs.

Power

Minnesota

Provided a claims prevention training seminar for a U.S. contractor that specializes in the design and construction of HRSGs.

Power

Illinois

On behalf of a manufacturer of HRSGs, analyzed an EPC contractor’s $35 million claim regarding a lump-sum contract to design and build a gas-fired power plant. Assessed the EPC contractor’s allegations regarding the constructability of the HRSGs and the delay and disruption impact of those problems on its work.

Power

California

Analyzed an HRSG manufacturer’s responsibility and liability for delays, scope of work changes related to increased piping quantities, and back charges from a general contractor on the installation of four waste HRSGs.

CONTACT US

Experience Matters

Our experts are ready to help.

Long International 25th Anniversary Logo

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.