Archive

On behalf of an African country, provided a rebuttal report and testimony in international arbitration regarding a claimant’s alleged value of its lost business opportunity after performing, at its own expense and risk, engineering and project development services for a port and rail project that it was not awarded. Evaluated the class of the claimant’s estimates of the project costs before and after it performed its de-risking of the project to lower project costs and determined that the estimates were inaccurate based on the information that was available to prepare the estimates. Thus, found that the claimant’s alleged project savings and its claim amount were speculative.

Transportation

Mozambique

On behalf of an African country, provided a rebuttal report and testimony in international arbitration regarding a claimant’s alleged value of its lost business opportunity after performing, at its own expense and risk, engineering and project development services for a port and rail project that it was not awarded. Evaluated the class of the claimant’s estimates of the project costs before and after it performed its de-risking of the project to lower project costs and determined that the estimates were inaccurate based on the information that was available to prepare the estimates. Thus, found that the claimant’s alleged project savings and its claim amount were speculative.

Transportation

Washington DC

Provided support to management team including schedule coordination, review and development of Baseline CPM Schedule for the $62 million New York Avenue Metrorail Station. The project consisted of the construction of a new “drop in” metro station, including all track work and connections.

Transportation

Massachusetts, Connecticut, New York

Assisted Amtrak in preparation and presentation of claims against defendant EPC contractor under the Federal False Claims Act on the installation of a high speed rail from Boston to New York.  Client asserted that defendant contractor had improperly billed the government for substantial amounts that did not represent actual increased costs to the contractor but were rather the result of gross miscalculations of alleged increased costs due to scope changes, schedule impacts of changes and resulting acceleration costs.  Claims were settled prior to trial with the contractor agreeing to withdraw over $25 million of invoiced amounts.

Transportation

California

Performed quality control and reasonableness review of a schedule delay analysis for a tunnel-boring contract on the Los Angeles metro subway project.

Transportation

Minnesota

On behalf of a contractor, analyzed damages to rebut a $52 million claim from the owner on a large wastewater tunnel. Audited and reconciled $166 million in actual costs versus an after the fact estimate of $114 million.

Transportation

California

Priced and negotiated change orders for the Bay Area Rapid Transit District on a $65 million train control contract. Evaluated entitlement, prepared schedule analyses, wrote findings of fact, and negotiated change orders.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.