Archive

Provided claims prevention training seminars for a mineral processing engineering firm in Denver, Tucson, and Mexico City. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.

Mining and Mineral Processing

Colorado, Arizona

Provided claims prevention training seminars for a mineral processing engineering firm in Denver, Tucson, and Mexico City. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.

Mining and Mineral Processing

Colorado

On behalf of an owner, developed cash flow economic evaluation computer models and prepared capital and operating cost estimates and economic analyses used in the negotiation of the $1.1 billion project loan guarantee for a shale oil project.

Refineries, Petrochemical, and Chemical

Colorado

Analyzed an owner’s errors and omissions claim against the design contractor on a condensate plant project.

Water, Wastewater, Dams, and Marine

Colorado

Provided schedule delay and damages analysis and prepared an expert report and a rebuttal report for a general contractor in a claim against the owner on the construction of a new wastewater treatment facility.

Building Construction

Colorado

Performed schedule delay analysis, damages analysis, preparation of an expert’s report, and presentation of testimony in deposition for a general contractor’s surety in defense of a claim that an electrical subcontractor submitted on the construction of a correctional facility in Arapahoe County.

Pipelines and Utilities

Colorado

Performed damages and schedule analyses for a contractor in a $1.3 million dispute with its earthwork and utilities subcontractor. Submitted an expert report that asserted $300,000 in damages and defended a $1 million counterclaim. Prepared all damages and schedule analyses and provided testimony in both deposition and arbitration. The contractor received a favorable award.

CONTACT US

Experience Matters

Our experts are ready to help.

Long International 25th Anniversary Logo

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.