Assisted Amtrak in preparation and presentation of claims against defendant EPC contractor under the Federal False Claims Act on the installation of a high speed rail from Boston to New York.  Client asserted that defendant contractor had improperly billed the government for substantial amounts that did not represent actual increased costs to the contractor but were rather the result of gross miscalculations of alleged increased costs due to scope changes, schedule impacts of changes and resulting acceleration costs.  Claims were settled prior to trial with the contractor agreeing to withdraw over $25 million of invoiced amounts.

Transportation

Massachusetts, Connecticut, New York

Assisted Amtrak in preparation and presentation of claims against defendant EPC contractor under the Federal False Claims Act on the installation of a high speed rail from Boston to New York.  Client asserted that defendant contractor had improperly billed the government for substantial amounts that did not represent actual increased costs to the contractor but were rather the result of gross miscalculations of alleged increased costs due to scope changes, schedule impacts of changes and resulting acceleration costs.  Claims were settled prior to trial with the contractor agreeing to withdraw over $25 million of invoiced amounts.

Power

Connecticut

Analyzed a $50 million delayed start-up claim on a 500 MW power plant. Evaluated project delays and cost impacts related to the Heat Recovery Steam Generator (HRSG) collapse.

Power

Connecticut

Provided analysis in defense of a $7.1 million claim brought by a mechanical erection subcontractor for increased scope, delay, extended overheads, and lost productivity on a $189 million simple cycle cogeneration plant.