Gas, Gasification, GTL, LNG, and NGL
On behalf of an owner, analyzed delays and project management performance deficiencies in defense of a $40 million claim of an EPC contractor. The claim involved additional overhead and fee on a cost reimbursable contract for the management of the design and construction of an LNG terminal project that was delayed over 18 months. Analyzed deficiencies in the EPC contractor’s schedules and analyzed concurrent delays. Prepared the basis of a counterclaim by the owner against the EPC contractor.