Oil Sands

Share

On behalf of an insurance company, analyzed a $500 million claim for business interruption losses due to delays to the startup and commissioning of an upgrader refinery that was built to process synthetic crude oil from an oil sands production facility. The delays were allegedly caused by a fire at the oil sands production mine site, which delayed the transport of bitumen to the refinery through a 200-plus-mile pipeline. Prepared detailed CPM schedule analyses and an expert witness report. Designated as a CPM expert witness in support of the ICC arbitration in Alberta.