Pipelines and Utilities

Share

On behalf of an owner, analyzed an EPC contractor’s $43 million claim on behalf of an owner involving hundreds of alleged P&ID changes to the FEED design of a compressor station and pipeline project. Also analyzed resulting delay to the completion of the project, and the technical entitlement to the P&ID changes based on standard industry practice for design development, the owner’s specifications, and the timing of the changes.