On behalf of an owner, analyzed a French contractor’s $14 million delay and increased quantities claim on a 36-inch gas pipeline and valve station project. Reviewed the owner’s ITB packages, contracts, project controls procedures, and contract administration procedures and presented a claims prevention seminar. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.