Power
Performed schedule delay expert witness services with respect to a $34 million dispute between an electrical power generator and a consortium of power distributors. Issues involved the analysis of concurrent delay. Services included a delay analysis with respect to a forced outage resulting from an alleged force majeure event. Identified and quantified schedule impacts that resulted from accelerating the start of planned outage work that the power plant operator moved to be in parallel with necessary work associated with the forced outage. Provided testimony that addressed impacts to the outage affected by moving the start of planned outage work to be performed concurrently with forced outage work.