Assisted a contractor in resolving a dispute related to design changes and late and deficient owner-supplied materials. Prepared and reviewed notice letters and provided input for negotiations for a combined heat and power (CHP) project aimed to replace two old boilers and two steam turbines from an existing power plant. Proposed installed capacities for the project were 450MW of thermal heat and approximately 30MW of electricity. The thermal heat was supplied to an oil refinery and a petrochemical plant within the same site while electricity was supplied to the grid. The project also produced demineralized water.