On behalf of an owner, evaluated a contractor’s expert report and €18 million delay and disruption claim concerning the replacement of emergency diesel generators on a nuclear power plant in Finland. Assessed the expert’s time extension analysis, which was found to lack an assessment of the critical path of the work. The claim was ultimately rejected.