Power
Assisted a general contractor in a $2 million dispute with the owner of a 200 MW power plant in New Brunswick. Issues involved increased labor costs associated with late delivery of owner-supplied equipment, late design information, and defective design information. The case was settled during negotiation on terms favorable to the client.