Power
The project centered on the installation of a 230 kV transmission line: 24 miles underground and 3.5 miles overhead, through an extremely diverse and environmentally sensitive and challenged series of districts. The major infrastructure subcontractor alleged major delay and disruption impacts caused by the main contractor. Engaged to provide claim support services to the main contractor against the subcontractor’s claims. Prepared a defense position paper involving a CPM analysis, disruption analysis, and contract entitlement to rebut the subcontractor’s expert report, which ultimately resulted in mediation proceedings and a series of settlement negotiations. Also provided claims avoidance training and lessons learned reviews to the main contractor construction team to facilitate improved management of future similar projects.