Refineries, Petrochemical, and Chemical
On behalf of an owner, analyzed entitlement, schedule delay and damages related to a contractor’s $12 million claim against a major international chemical company associated with the construction of two process units in an existing chemical plant. The initial EPC contractor was terminated and sought recovery of its cost overruns as a result of field change orders. The owner alleged that the work was defective as a result of engineering errors, field installation errors, and welding defects.