Transportation
Provided CPM scheduling on the Molton section of the $800 million San Joaquin Hills Transportation Corridor project in Irvine. This project had over 100 new CIP bridge structures, miles of driven piles, retaining walls, and storm drains, in addition to over 1 million CY of cut/fill earthwork. The Molton Section “Working Schedule” included 1,544 activities.