Transportation
Developed and maintained updates of the Baseline CPM Schedule for the $230 million Brooklyn-Queens Expressway (BQE) project. Provided schedule expertise, project administration, coordination, analysis, and negotiation of all time-related issues. The schedule was resource loaded with 2,840 activities.