PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Industrial and Manufacturing

Virginia

On behalf of a construction manager, analyzed a mechanical contractor’s contract and quantum meruit claim for disputed changes in scope, delays, and loss of productivity on the installation of piping systems on a computer microchip manufacturing facility. Presented testimony in arbitration.

Industrial and Manufacturing

Alberta, Canada

On behalf of an owner, performed an audit of the EPCM and general contractor’s cost records to identify potential billing discrepancies and problems on cost reimbursable contracts for a calciner expansion project.

Industrial and Manufacturing

Indiana

On behalf of an owner, provided schedule delay analysis, cost analysis, and litigation support of a $400 million blast furnace and coke oven battery project involving analysis of construction cost and schedule overruns and the adequacy of the engineering design.

Industrial and Manufacturing

South Carolina

Assisted an EPC contractor with a $10 million claim against an owner for increased costs associated with increased scope of work, project delays and disruption, and loss of labor productivity arising from subsequent acceleration on the design, delivery and construction of an additional line for the production of polyester chips for use in plastic soda bottle manufacturing.

Industrial and Manufacturing

Illinois

Prepared damages analyses on a dispute on a steel mill expansion project. Responsible for a unit price variance analysis and estimating costs for civil, concrete, mechanical, and electric work.

Industrial and Manufacturing

Louisiana

On behalf of an EPC contractor, provided schedule delay analysis as well as contractor scheduling and progress reporting during the execution of a steam supply optimization project consisting of equipment erection and piping fabrication and installation for a package boiler system at a manufacturing facility in Louisiana.

Industrial and Manufacturing

Florida

On behalf of an owner, analyzed a $60 million claim from a general contractor related to alleged project delay, increased scope, and loss of labor productivity. The project was for the expansion of an existing cement manufacturing plant in Florida and involved the construction of an additional 2,800-ton-per-day production line from raw material handling through bulk material load out. Performed schedule quality assurance reviews of the contractor’s contemporaneous schedules to correctly quantify project delay and disruption from alleged late delivery of owner equipment. Worked closely with the owner to resolve problems contained within the contractor’s contemporaneous schedules such as open-end activities, overuse of constraints, missing original scope, incorrect as-built dates, missing as-built dates, and missing logic links.

Industrial and Manufacturing

Indiana

On behalf of an insurer, evaluated property damage claims associated with flood-damaged industrial buildings and manufacturing facilities following a flood. Prepared comparative cost estimates for the damaged equipment and facilities to test the reasonableness of the damage claims alleged by the owner.

Industrial and Manufacturing

Texas

Assisted a supplier of proprietary equipment in defending against a $20 million claim on a project involving the design, delivery and construction of a new cement production line from ore receiving to clinker storage and loadout. The general contractor claimed for increased costs allegedly due to delays, disruption and labor impact arising from late delivery of design data and proprietary equipment, and a defective design. The case was arbitrated in Texas. The client was found liable for only a portion of disputed extra work.

Industrial and Manufacturing

South Dakota

Prepared a contractor’s delay and loss of productivity claim against an owner cooperative on the construction of a $32 million soybean processing plant. Developed a document database, prepared a detailed schedule analysis, and calculated the contractor’s entitlement to delay and loss of productivity damages as a result of the defective design by the process equipment licensor and late delivery of equipment.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.