Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Industrial and Manufacturing

Alberta, Canada

On behalf of an owner, evaluated delays and cost overruns on an insulation manufacturing facility in Alberta. Analyzed schedule and cost data in support of the owner’s $28 million counterclaim against an EPC contractor’s $20 million claim. Testified as CPM schedule and cost expert witnesses for the arbitration.

Industrial and Manufacturing

Oregon

Performed an entitlement and schedule analysis on a $60 million dispute arising from a steel mill expansion project. Reviewed RFIs, drawing changes, and change orders to identify and apportion schedule impacts.

Industrial and Manufacturing

Colorado

Prepared an electrical contractor’s claim involving engineering delay, errors and omissions resulting in workarounds and construction delays on the installation of life safety systems and instrumentation and control automation on a silicone chip plant and cleanroom facility in Colorado Springs. Performed a schedule analysis of delay impacts due to engineering rework and added change order work, causing schedule compression and acceleration with trade stacking, overmanning of crews with a shortage of qualified labor causing productivity loss due to overtime fatigue, lack of coordinated drawings, late material delivery, and substandard supervisory management and cost controls by the construction manager.

Industrial and Manufacturing

Texas

Assisted a supplier of proprietary equipment in defending against a $20 million claim on a project involving the design, delivery and construction of a new cement production line from ore receiving to clinker storage and loadout. The general contractor claimed for increased costs allegedly due to delays, disruption and labor impact arising from late delivery of design data and proprietary equipment, and a defective design. The case was arbitrated in Texas. The client was found liable for only a portion of disputed extra work.

Industrial and Manufacturing

Florida

On behalf of an owner, analyzed a $60 million claim from a general contractor related to alleged project delay, increased scope, and loss of labor productivity. The project was for the expansion of an existing cement manufacturing plant in Florida and involved the construction of an additional 2,800-ton-per-day production line from raw material handling through bulk material load out. Performed schedule quality assurance reviews of the contractor’s contemporaneous schedules to correctly quantify project delay and disruption from alleged late delivery of owner equipment. Worked closely with the owner to resolve problems contained within the contractor’s contemporaneous schedules such as open-end activities, overuse of constraints, missing original scope, incorrect as-built dates, missing as-built dates, and missing logic links.

Industrial and Manufacturing

Illinois

On behalf of an equipment manufacturer, analyzed a $7 million claim by a contractor regarding extra work involving the structural steel installations on a new cement manufacturing plant. The analysis also involved the contractor’s claim that it constructively accelerated its work to overcome delays.

Industrial and Manufacturing

Maryland

Provided entitlement and damages analyses on an $11 million dispute arising from the construction of a semi-conductor fabrication facility. Prepared issue analyses related to mechanical and piping design changes and performed estimates on mechanical and piping work to analyze cost overruns.

Industrial and Manufacturing

Washington

Analyzed a Swedish contractor’s delay and disruption claim involving the design and construction of a pulp and paper mill.

Industrial and Manufacturing

Indiana

On behalf of an insurer, evaluated property damage claims associated with flood-damaged industrial buildings and manufacturing facilities following a flood. Prepared comparative cost estimates for the damaged equipment and facilities to test the reasonableness of the damage claims alleged by the owner.

Industrial and Manufacturing

South Dakota

Prepared a contractor’s delay and loss of productivity claim against an owner cooperative on the construction of a $32 million soybean processing plant. Developed a document database, prepared a detailed schedule analysis, and calculated the contractor’s entitlement to delay and loss of productivity damages as a result of the defective design by the process equipment licensor and late delivery of equipment.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.