Power
ConnecticutProvided analysis in defense of a $7.1 million claim brought by a mechanical erection subcontractor for increased scope, delay, extended overheads, and lost productivity on a $189 million simple cycle cogeneration plant.
PROJECT EXPERIENCE
Provided analysis in defense of a $7.1 million claim brought by a mechanical erection subcontractor for increased scope, delay, extended overheads, and lost productivity on a $189 million simple cycle cogeneration plant.
Analyzed a contractor’s $22 million delay and disruption claim against the owner of a 3x1 combined cycle power plant in Baytown. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.
On behalf of an owner, analyzed change orders, delays, acceleration, and loss of productivity impacts associated with the relocation of an existing gas-fired turbine generator and the construction of a new HRSG in an existing industrial plant. This project involved the defense against the contractor’s claim and preparation of the owner’s liquidated damages counterclaims. Testified in mediation, which resulted in a successful settlement of the dispute.
Developed a contractor’s $21 million delay and disruption claim against the owner of a 4x2 combined cycle power plant in Romoland. The scope of work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.
On behalf of a nuclear stem system licensor and supplier, analyzed schedule delay, productivity loss, and direct damages totaling over $1 billion allegedly resulting from problems related to hydrodynamic loads on a nuclear power plant reactor building. Developed a document database comprising hundreds of thousands of documents, and managed the technical experts providing the design analysis.
The project centered on the contract to design and build a 663 MW sub-critical pulverized coal-fired plant addition to an existing brownfield facility. This was a full EPC contract involving multiple stakeholders including a joint venture between the major contracting entities and power island suppliers. Managed a team engaged to provide risk management and claims avoidance advisory and training services to the on-site project teams. Services also included claims avoidance management both on a term and “as required” basis to facilitate early settlement of project problems and avoid lengthy disputes. The project was completed with no major claims or dispute issues.
Provided claims analysis and cost and schedule analyses. Prepared a rebuttal report regarding insurance claims related to defective flue gas desulfurization systems on four coal-fired power plant projects.
Analyzed a contractor’s delay and disruption claim against the owner of a 2x1 combined cycle power plant in Boston. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.
Assisted a contractor in resolving a dispute related to design changes and late and deficient owner-supplied materials. Prepared and reviewed notice letters and provided input for negotiations for a combined heat and power (CHP) project aimed to replace two old boilers and two steam turbines from an existing power plant. Proposed installed capacities for the project were 450MW of thermal heat and approximately 30MW of electricity. The thermal heat was supplied to an oil refinery and a petrochemical plant within the same site while electricity was supplied to the grid. The project also produced demineralized water.
On behalf of a manufacturer of HRSGs, analyzed a contractor’s claim for delay, acceleration, scope of work changes, and loss of productivity on the installation of three waste HRSGs.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.