Refineries, Petrochemical, and Chemical
U.S. Virgin IslandsOn behalf of a contractor, analyzed its pipe fabrication loss of productivity claim on a project involving an upgrade to an existing refinery.
PROJECT EXPERIENCE
On behalf of a contractor, analyzed its pipe fabrication loss of productivity claim on a project involving an upgrade to an existing refinery.
On behalf of a Japanese EPC contractor, prepared a claim, developed a document database, and analyzed costs and schedules for a $450 million fertilizer plant. Prepared a $100 million claim against the owner, which was abandoned as a result of the Gulf War. Successfully negotiated one Turkish and two Korean subcontractors’ claims against the Japanese prime contractor.
Provided construction claims consulting services, claims analysis, and change order reviews related to a methanol plant construction project. Reviewed the EPC contractor’s contract and the EPC contractor’s unresolved claims and change order requests to develop more complete descriptions of the claim issues, evaluate the merits of the claims, and prepare a summary of the claim documentation to support the client’s settlement discussions with the EPC contractor.
On behalf of a major U.S. oil company, analyzed a Korean contractor’s $75 million claim involving delay, disruption, and acceleration on a major oil terminal project. Assessed the contractor’s CPM schedules, change orders, and increased staffing claims. Also evaluated the owner’s counterclaims due to late and defective work.
On behalf of an EPC contractor, analyzed delay and acceleration claims on the EPC of an ammonia plant project.
On behalf of an owner, performed a schedule quality assurance review of an EPCM contractor’s EPC schedule on a new methanol plant.
On behalf of an owner, analyzed various contractor’s delay and change order claims on a major gasoline optimization project, including modifications to an existing FCCU unit, a new alky-acid unit, an isomerization unit, a new heavy naphtha hydrotreater and continuous catalytic regeneration platformer unit, and offsites facilities modifications. Claim evaluations included an assessment of the integrity of the contractor’s baseline and schedule updates, preparation of alternative impact analysis of delays allegedly caused by scope changes as well as concurrent delays caused by the contractor. Also conducted cost support reviews for the change order amounts, recalculation of time-related costs based on delay analyses, and determination of damages based on assessment of contractual entitlements under the terms of the contract. Participated during negotiations to achieve settlement of the change order claims.
On behalf of an owner, analyzed cost overruns incurred by a contractor on an oil terminal project in Alberta. Reviewed and compared bid package drawings with issued for construction drawings, welding data, and other information to determine if the owner had a basis for disputing the contractor’s costs. Participated in mediation to resolve the dispute.
Retained by the owner of a surfactants expansion project to defend a claim by an electrical contractor for increased costs and loss of productivity. Evaluated standard of care, schedule, causation, labor productivity (including loss productivity due to changes), and damages.
On behalf of an owner, analyzed a contractor’s $11 million claim involving disputed change order work, loss of productivity, late materials deliveries, and other delay events on a new petrochemical plant project. Issues involved customs clearance delays and inadequate project management by the contractor.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.