Transportation
Alberta, CanadaOn behalf of a contractor, analyzed cost overruns associated with the construction of a heavy haul road in Alberta.
PROJECT EXPERIENCE
On behalf of a contractor, analyzed cost overruns associated with the construction of a heavy haul road in Alberta.
Performed financial and schedule audits for the Los Angeles County Transportation Commission on metro subway projects. Reviewed project budgets, contractor schedules, and construction manager monthly progress reports, and advised the County of potential cost overruns, schedule delays and reporting deficiencies.
Provided cost and CPM scheduling services on a City of Las Vegas Traffic and Communication project. Developed and monitored resource-loaded completion schedules for the remaining work. Performed a retrospective CPM schedule analysis to prove change order impacts to the critical path of the project. Used activity-based costing techniques to appropriately allocate extended corporate and project overhead costs due to a 6-month suspension period. Performed productivity studies and provided resource and cost projects used for cash flow and cost-to-complete purposes. Successfully performed change order pricing and negotiations ($750K) with the owner for numerous design impacts.
As part of the claim scheduling team, provided support documentation, presentation, and negotiation for a $30 million claim on the $400 million Boston Central Artery Project “Big Dig.”
Prepared project schedule for the general contractor on a highway construction project, analyzed delays, and prepared written reports for time extension requests to the project owner. Testified in arbitration.
Developed the Baseline CPM Schedule for the $76 million Route 18 Extension Section 2A Highway Project.
Provided contract/entitlement analysis and prepared detailed as-planned and as-built schedule analyses for a contractor on a highway construction project in Pennsylvania. Assisted the contractor to prepare a recovery schedule to mitigate construction delays caused by differing site conditions.
On behalf of a contractor, analyzed damages to rebut a $52 million claim from the owner on a large wastewater tunnel. Audited and reconciled $166 million in actual costs versus an after the fact estimate of $114 million.
Provided scheduling support to the estimating team for the $77 million Highbridge Yard Maintenance Facility. Developed pre-bid schedule and aided in the development of Baseline CPM Schedule. The project consisted of the construction of a 62,000 SF rail car maintenance facility (ten car lengths) with two tracks and the installation of associated maintenance and repair equipment. The facility also included an additional 8,300 SF of office space and employee locker rooms located on the second floor. Other project components included the construction of 35,000 feet of track along with 32 switches and electric substation, as well as an employee station.
Prepared an owner/operator’s claim against a major railroad for causing delays and cost overruns during the construction of fiber optic communications systems along the railroad’s right-of-ways. Developed schedule delay analysis of each of the right-of-ways along which the fiber optic cable was installed in trenches. Identified detailed daily documentation that identified railroad interference or lack of support for the installation of the work.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.