
June 10, 2024
The Schedule Basis Memorandum: Considerations for Common Risks That May Cause Delay
This is the third blog post in a six-part series about the schedule basis memorandum. The first post defines the schedule basis memorandum and discusses its key purpose for CPM scheduling, and the second post identifies information to include in the document. The third post identifies considerations for common risks that may cause delay on large and complex EPC projects, and the fourth post focuses on three of those risks: competing project considerations, owner review comments, and weather considerations. The fifth post discusses common risks associated with labor camp size considerations, and the sixth post discusses labor camp catering and other service risks.
Schedule Basis Considerations for Common Risks That May Cause Delay on Large and Complex EPC Projects
Certain risks are inherent in performing large and complex EPC projects that often result in claims and disputes between the contractor and the owner. These inherent risks should be thoroughly addressed when developing a schedule basis document for executing a project. Many of the sections and sub-sections identified in Table 2 in the second blog post in this series require detailed consideration to properly document the schedule basis. The following are examples of items that should be examined closely during schedule development to ensure that the planned project completion date is feasible and that potential requests for time extensions due to alleged delays can be properly evaluated against a reasonable baseline:
- Labor Productivity Assumptions
- Competing Project Considerations
- Potential Owner Delays in Providing Review Comments
- Weather Considerations
- Camp Size Considerations
- Camp Catering and Other Service Considerations
It is recommended that the schedule basis memorandum document details assumptions for these issues. If a claim or dispute arises from one or more of the above issues, the schedule basis memorandum documents what was known or not known at the time of the CPM schedule development, and what assumptions or allowances were considered. Consequently, the schedule basis memorandum could be the deciding document to either validate or discredit a contractor’s claim against an owner. This post and subsequent posts discuss these schedule basis considerations to promote awareness for both contractors and owners regarding potential claims and disputes.
Labor Productivity Assumptions
An EPC contractor’s estimated labor productivity is a significant factor for determining the labor requirements needed to develop activity durations. Productivity assumptions should be based on: 1) a contractor’s experience in performing work in the project location or as close in proximity as possible, and 2) the availability and skills of the labor to be utilized for the project. If the labor productivity assumptions are overly optimistic, then the durations of construction activities will likely be too short, and the actual durations will become extended, resulting in schedule delays. For example, if durations for construction work are based on an average productivity factor of, say, 1.7 compared to U.S. Gulf Coast, and the actual productivity turns out to be 3.4 rather than 1.7, then the planned durations could be 50 percent shorter than required from the outset, and the actual construction work may take twice as long as planned to perform.
Therefore, it is vital that both the EPC contractor and owner fully understand the productivity factors used in the schedule basis for developing activity durations. If the owner believes that the EPC contractor’s estimated labor productivity factors for the project are overly optimistic as documented in the schedule basis, then the owner should request that the EPC contractor prepare alternative schedules and manpower loadings using a range of productivity factors that may depict a more appropriate and realistic schedule basis for the project.
ADDITIONAL RESOURCES

Blog
Discover industry insights on construction disputes and claims, project management, risk analysis, and more.
MORE

Articles
Articles by our engineering and construction claims experts cover topics ranging from acceleration to why claims occur.
MORE

Publications
We are committed to sharing industry knowledge through publication of our books and presentations.
MORE
RECOMMENDED READS
Problematic Construction Contract Clauses
This is the first post in a series that discusses construction contract terms that cause difficulties and give rise to claims.
READ
Deficient and Defective Contract Documents: An Introduction
This is the first post in a seven-part series that discusses defective and deficient contract document claims.
READ
Contract Language: Defining Standard of Care and Good Industry Practice
Language in EPC and EPCM contracts defines standards of care and excellence, good industry practice, and required skills and capacity to perform.
READ