Water, Wastewater, Dams, and Marine
Alberta, CanadaPrepared detailed as-planned and as-built schedule analyses for a contractor on a dam project. Participated in negotiations between the contractor and the Province of Alberta.
Archive
Prepared detailed as-planned and as-built schedule analyses for a contractor on a dam project. Participated in negotiations between the contractor and the Province of Alberta.
Prepared detailed as-planned and as-built schedule analyses for a contractor on a dam project. Participated in negotiations between the contractor and the Province of Alberta.
On behalf of an insurance company, analyzed a $500 million claim for business interruption losses due to delays to the startup and commissioning of an upgrader refinery that was built to process synthetic crude oil from an oil sands production facility. The delays were allegedly caused by a fire at the oil sands production mine site, which delayed the transport of bitumen to the refinery through a 200-plus-mile pipeline. Prepared detailed CPM schedule analyses and an expert witness report. Designated as a CPM expert witness in support of the ICC arbitration in Alberta.
On behalf of an owner, performed an audit of the EPCM and general contractor’s cost records to identify potential billing discrepancies and problems on cost reimbursable contracts for a calciner expansion project.
On behalf of an insurance company, analyzed a $200 million insurance claim for non traditional coverages resulting from delays and cost overruns on the construction of an oil sands mine facility and upgrader unit in Alberta. Prepared expert witness reports in support of the ICC arbitration.
Developed a thesis for an Equitable Adjustment. Reviewed existing cost calculations and data and prepared Phase I findings regarding a claim for Equitable Adjustment for a law firm on behalf of a heavy civil contractor regarding the rehabilitation of a mine tailings management area in Manitoba.
Performed a high-level review of an insurer's flood and fire analysis spreadsheets. Assessed reasons for claimed cost denials and/or reductions and reviewed documentation to preliminarily address cost denials and/or reductions. Developed a rebuttal report to claimed cost denials and reductions for a 237-bed, long-term-care living/nursing facility.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.