Prepared a report, damage analysis, and schedule analysis on behalf of a subcontractor for a $450,000 change order on the construction of a parking structure with post-tensioned structural concrete. Prepared an as-built “but-for” schedule analysis and calculated claimed costs.

Building Construction

Colorado

Prepared a report, damage analysis, and schedule analysis on behalf of a subcontractor for a $450,000 change order on the construction of a parking structure with post-tensioned structural concrete. Prepared an as-built “but-for” schedule analysis and calculated claimed costs.

Building Construction

North Carolina

On behalf of a contractor, provided claim preparation services on a Federal Reserve Bank project, including entitlement analysis and preparation of a detailed as-built but-for CPM schedule analysis to determine responsibility for delay time and damages.

Building Construction

Texas

Provided litigation support for the construction cost overruns and delays for several commercial building projects including a luxury hotel and a major office building.

Building Construction

California

Performed schedule delay analysis, prepared an expert report, and presented testimony for the architect/engineer on a high-rise commercial building in Westwood.

Building Construction

Colorado

Provided schedule and damages analysis services and prepared a $1.2 million claim for a contractor that built a grocery store. Responsible for auditing and recoding invoices and timesheets, preparing a cost variance analysis and calculating damages, recreating the as-built schedule, and identifying and apportioning delays.

Building Construction

Georgia

On behalf of an insurance company, analyzed a contractor’s claim for costs associated with repairs to damage resulting from a tower crane jacking failure on a mixed-use development project in Atlanta. Prepared detailed analyses and reports to identify reasonableness of costs claimed in preparation of negotiation and settlement among the insurers, insured, and insured’s contractor.

Building Construction

Georgia

Reviewed and performed delay and cost analysis services for a mixed-use and retail development project in Roswell. Prepared detailed schedule, damages, and delay analysis in preparation of litigation and support for trial.