Archive

EPC design build of a 500 MW gas-fired power plant. The project was significantly delayed and disrupted due to local unavailability of labor resources despite union agreements to provide the required construction manpower. Prepared a force majeure claim based on lack of available local labor and other resources. This involved considerable research into area and regional labor usage, related area and regional construction facilities, and union services interfaces. Submitted a heavily researched paper to the client including supporting CPM analysis and contract entitlements to facilitate settlement negotiations. The main contractor succeeded in recovering additional monies and avoiding liquidated damages.

Power

Rhode Island

EPC design build of a 500 MW gas-fired power plant. The project was significantly delayed and disrupted due to local unavailability of labor resources despite union agreements to provide the required construction manpower. Prepared a force majeure claim based on lack of available local labor and other resources. This involved considerable research into area and regional labor usage, related area and regional construction facilities, and union services interfaces. Submitted a heavily researched paper to the client including supporting CPM analysis and contract entitlements to facilitate settlement negotiations. The main contractor succeeded in recovering additional monies and avoiding liquidated damages.

Power

Singapore

The project centered on disputes between a major contractor and a mechanical/electrical subcontractor on alleged delay and disruption impacts during the construction of a 380 MW power facility due to alleged late information, delayed procurement, and changes. Project completion was significantly delayed, and the subcontractor claimed the contractor caused the negative schedule impacts, subsequently submitting a request for an equitable adjustment (REA) and filing for arbitration. Team leader engaged to consult on the main contractor’s defense of the claim both during the contract execution works and the post completion arbitration events. This involved day-to-day contract administration, claims preparation, and overall management of claims team, outside counsel, and experts.

Power

Connecticut

Analyzed a $50 million delayed start-up claim on a 500 MW power plant. Evaluated project delays and cost impacts related to the Heat Recovery Steam Generator (HRSG) collapse.

Power

United Kingdom

EPC design build of a 280 MW gas-fired combined cycle power expansion to a refinery brownfield site. Managed and directed contract administration and claims procedures team. Defended and negotiated a series of owner/subcontractor claims against the EPC contractor. Prepared a force majeure weather impact claim.

Power

Oregon

The project involved disputes among an owner, main contractor, and joint venture power island equipment supplier regarding damage to the combustion turbine (CT) caused by through projectiles in the power stream. The multi-party dispute involved both contract and insurance claims for delay, disruption, liquidated damages, and direct damage reparation works to the CT start-up operations. Managed claims team that was engaged to consult on both the contract and the insurance claims for the main contractor, which involved delay, disruption, and damages analyses for a series of settlement negotiations and mediation. Ultimately, the completion of the damaged CT works had to be factored into the process and the plant restored to full operational capability. Settlement talks ultimately succeeded, and formal litigations proceedings were avoided.

Power

Pakistan

On behalf of an owner, reviewed an EPC contractor’s $12 million force majeure delay claim due to heavy rain and flooding. Provided schedule delay analysis services related to the 404 MW combined cycle gas turbine power plant. Scope of work included review and analysis of the EPC contractor's extension of time claim and preparation of the client's response.

CONTACT US

Experience Matters

Our experts are ready to help.

Long International 25th Anniversary Logo

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.