Performed schedule delay and damages analysis and prepared the claim document for the electrical subcontractor on the glycol recovery project at Denver International Airport. The claim was prepared as a pass-through claim to be submitted through the general contractor’s surety to the project owner.

Transportation

Colorado

Performed schedule delay and damages analysis and prepared the claim document for the electrical subcontractor on the glycol recovery project at Denver International Airport. The claim was prepared as a pass-through claim to be submitted through the general contractor’s surety to the project owner.

Transportation

California

Provided pre-bid scheduling using Primavera for the $180 million San Diego International Airport expansion and infrastructure project. Also reviewed and approved the contractor’s schedules. This project included CIP bridge structures, utility relocations, demolition of existing bridge structure, grading and paving for detours and airport parking.

Transportation

Colorado

Provided contract administration, schedule development, schedule delay and damages analysis, and claim preparation services for several contractors on the construction of buildings and facilities at the new Denver International Airport.

Transportation

Kansas

Provided schedule delay analysis, prepared an expert report, and presented testimony in deposition and arbitration for a general contractor in defense of claims submitted by a glass/glazing subcontractor on the Kansas City Airport renovation project.

Transportation

Wyoming

On behalf of an owner, evaluated a contractor’s claim on a new airport terminal building project.

Transportation

California

On behalf of the general contractor, provided claim preparation, schedule and damage analyses, and litigation support services for the $100 million John Wayne Airport expansion project. Prepared detailed as-planned and as-built schedule analyses.

Transportation

Colorado

Provided project management and control services for a contractor providing fire alarm and voice paging systems work on Concourses A, B, and C, the airport office building, and the terminal complex at the Denver International Airport. Assisted client in cost control monitoring, schedule interfaces, change negotiations, and problem resolutions on a $12 million contract. Prepared financial and schedule analyses for the project and interfaced with the project management team for monthly pay applications and resolution of issues. Assisted in the client’s successful settlement of $6 million of outstanding changes with the owner due to unexpected changed conditions and third party contractor interference.

Transportation

Nigeria

On behalf of a contractor, prepared a response to an owner’s experts’ reports for an ICC arbitration in London regarding the reasonableness of a bid estimate and the cost to complete an airport project.