Articles and Presentations of Interest

The following articles have been authored by Long International’s experts. Topics ranging from Acceleration Claims to Why Claims Occur are covered in the articles listed below. The authors of these articles would be personally delighted to answer any questions you may have about them. For additional information, please contact Dan Copeland, Director of Business Development and Marketing, at (540) 868-8506.

 

Featured Article

Reservation of Rights to Make a Cumulative Impact Claim

 

Other Long International Articles

Acceleration Claims on Engineering and Construction Projects

Analysis of Concurrent Delay on Construction Claims

Analysis of Concurrent Pacing/Delay

As-Built But-For Schedule Delay Analysis

Assessment of Problems Associated with Poor Project Management Performance

Construction Claims for Variation in Quantity

Construction Claims in South America

Construction Claims Prevention

Construction Contract Notice Letters

Contract Scheduling Provisions

Cumulative Impact Claims

Defective and Deficient Contract Documents – A 2013 Update

Developing Subcontract Pricing as Applied to Building Construction

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

Document Database Considerations

Effective Change Order Management

EPC Contract Risk Analysis Associated with Onshore Projects in Developing Countries

Evaluation of Changes in Process Plant Projects

Forensic Schedule Assurance Review: A Vital Step Before Starting a Detailed Schedule Analysis

Glossary of Terminology – Scheduling, Estimating, Project/ Construction Management, Contract Administration, and Construction Claims Terminology for Engineering and Construction Projects

Long International’s Schedule and Delay Analysis Methodologies

Preserving Your Claim Through Documentation

Schedule Quality Assurance Procedures

The Impact of Poor Contemporaneous Project Records on Claims Preparation and Expert Analyses

The Importance and Value of Notice Provisions in Construction Contracts

Typical Problems Leading to Delays, Cost Overruns, and Claims on Process Plant and Offshore Oil & Gas Projects

Why Claims Occur – The Red Flags

Construction Today, October 14, 2011

 

Presentations

Integrated Cost – Schedule Risk Analysis Using the Risk Driver Approach – Qatar PMI Meeting, February 19, 2014